Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam AACE-PSP Topic 4 Question 34 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 34
Topic #: 4
[All AACE-PSP Questions]

If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Emily
9 days ago
Historical production rates, easy peasy. Unless the project manager is a time-traveling, stock-trading physicist, in which case I'm completely lost.
upvoted 0 times
...
Jose
22 days ago
Black-Scholes model? Did they accidentally include a finance question in here? I'm just going to go with the option that makes the most sense - historical production rates.
upvoted 0 times
Elliot
1 days ago
I agree, historical production rates seem like the most logical choice.
upvoted 0 times
...
...
Almeta
1 months ago
I believe time impact analysis can also be helpful in estimating work package durations.
upvoted 0 times
...
Odette
1 months ago
The Eichleay formula? What is this, a complex equation contest? I'll take the straightforward approach and go with historical production rates. Keep it simple, you know?
upvoted 0 times
Laurel
23 days ago
Historical production rates are a reliable source for estimating work package durations.
upvoted 0 times
...
...
Nathalie
1 months ago
I agree with Barbra, historical production rates provide valuable information.
upvoted 0 times
...
Brynn
2 months ago
Time impact analysis? Seriously? What is this, a physics exam? I'll stick with the good old reliable historical production rates, thank you very much.
upvoted 0 times
Audry
18 days ago
User 1: Time impact analysis sounds complicated.
upvoted 0 times
...
Annalee
20 days ago
Yeah, time impact analysis does sound a bit complicated.
upvoted 0 times
...
Nichelle
1 months ago
I agree, historical production rates are a safe bet.
upvoted 0 times
...
...
Paulene
2 months ago
Historical production rates, for sure. That's the way to go when you don't have a detailed estimate. Worked for me on the last project.
upvoted 0 times
Filiberto
8 days ago
I agree, it's a reliable method when you don't have a detailed estimate.
upvoted 0 times
...
Merrilee
1 months ago
Historical production rates are definitely the way to go.
upvoted 0 times
...
...
Barbra
2 months ago
I think historical production rates can be used.
upvoted 0 times
...

Save Cancel