New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International AACE-PSP Exam - Topic 3 Question 45 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 45
Topic #: 3
[All AACE-PSP Questions]

Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

Show Suggested Answer Hide Answer
Suggested Answer: A

Analyze the Relationship Details: The table shows that Activity 3001 ('Excavation, Dam Site') and Activity 4001 ('Excavation, Spillway') have a Start-to-Start (SS) relationship with a lag of 15 days. A Start-to-Start relationship indicates that the successor activity (4001) can only start after a specified lag period once the predecessor activity (3001) begins.

Understand the Concept of Lag: In scheduling terminology, lag refers to a delay or waiting period between the start (or finish) of one activity and the start (or finish) of a dependent activity. Here, the 15-day lag means that Activity 4001 will commence 15 days after Activity 3001 has started.

Interpret the Relationship: The SS relationship combined with a lag indicates that the two activities (3001 and 4001) are not starting exactly at the same time but are still overlapping or concurrent. This concurrency happens after the lag period elapses.

Verify PSP Study Guide and Relevant Terminology: According to AACE International's Recommended Practices and the PSP Certification Study Guide:

Start-to-Start relationships are widely used to model overlapping work in schedules where one activity can start before its predecessor is fully complete (PSP Study Guide, Chapter on Scheduling Relationships and Constraints).

Lags provide flexibility to model realistic conditions where tasks start partially overlapping or with delays (PSP Study Guide, Section 2.2.4 Relationships).

Cross-Check the Answer Options:

Option A (Correct): Matches the described logic -- 'These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.'

Option B: Incorrect -- Lag is applied to the successor activity, meaning 4001 cannot start earlier than 3001.

Option C: Incorrect -- This relationship (SS with a lag) indicates concurrency, not series.

Option D: Incorrect -- Though concurrent, the lag makes the start times offset by 15 days, so they do not start at the same time.


PSP Study Guide (2019), Chapter 2A -- Schedule Development, Section 2.2.4 -- Relationships.

AACE International Recommended Practices, RP 10S-90, 'Cost Engineering Terminology.'

Total Cost Management Framework, Concepts of Activity Relationships and Scheduling Dependencies.

Contribute your Thoughts:

0/2000 characters
Dalene
6 days ago
Hmm, I was thinking B, but after looking at the diagram, C makes more sense. Good catch, guys.
upvoted 0 times
...
Reta
11 days ago
I agree with Elinore. The relationship between Activity 3001 and Activity 4001 clearly shows a 15-day lag, so C is the right choice.
upvoted 0 times
...
Elinore
16 days ago
Option C is the correct answer. The activities occur in series with a 15-day lag.
upvoted 0 times
...
Francine
21 days ago
I’m leaning towards option A, but I’m confused about the timing. Was it 15 days after or before?
upvoted 0 times
...
Magda
26 days ago
I feel like the answer is that they run concurrently, but I can't recall the specifics of the schedule.
upvoted 0 times
...
Refugia
1 month ago
I think we practiced a question like this where the lag was important. Could it be that they run in series with a 15-day lag?
upvoted 0 times
...
Jutta
1 month ago
I remember something about concurrent activities, but I'm not sure if it's 15 days after or before.
upvoted 0 times
...
Daron
1 month ago
I've got a strategy for this. I'll first identify the key information in the question and the image, then I'll systematically go through the answer choices and eliminate the ones that don't fit. That should help me arrive at the correct answer.
upvoted 0 times
...
Judy
2 months ago
Alright, let's think this through step-by-step. The question is asking about the relationship between Activities 3001 and 4001. The answer choices mention "concurrent" and "series" with a 15-day lag, so I'll need to determine which one of those best fits the information given.
upvoted 0 times
...
Nan
2 months ago
I'm a bit confused by the wording of the question. What does it mean by "indicated"? I'll need to read through the answer choices carefully to figure out what they're asking.
upvoted 0 times
...
Celeste
2 months ago
Okay, the question is asking about the "normal" schedule, so I'll need to focus on that. The image shows some kind of timeline, so I'll need to understand how the activities are related.
upvoted 0 times
...
Gilma
2 months ago
Hmm, this looks like a scheduling question. I'll need to carefully analyze the relationship between Activities 3001 and 4001 to determine the correct answer.
upvoted 0 times
...

Save Cancel