A company hosts a vSAN 7 stretched cluster for all development workloads. The original sizing of a maximum of 250 concurrent workloads in the vSAN cluster is no longer sufficient and needs to increase to at least 500 concurrent workloads within the next six months.
To meet this demand, the original 8-node (4-4-1) cluster has recently been expanded to 16 nodes (8-8-1).
Which three additional steps should the administrator take to support the current growth plans while minimizing the amount of resources required at the witness site? (Choose three.)
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vsphere.vsan-planning.doc/GUID-05C1737A-5FBA-4AEE-BDB8-3BF5DE569E0A.html
Shala
4 days agoBenton
9 days agoArthur
14 days agoSean
19 days agoHerminia
25 days agoDominga
30 days agoLai
1 month agoLisha
1 month agoNobuko
2 months agoAlba
2 months agoSylvia
2 months agoBen
2 months agoLouis
2 months agoKarma
2 months agoMarvel
4 months agoSalina
4 months agoColene
5 months agoVirgina
5 months agoNickolas
5 months agoDaisy
5 months ago