Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

US Green Building Council LEED-AP-BD+C Exam - Topic 10 Question 31 Discussion

A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?
A) Revise the documentation and resubmit the form
B) Abandon meeting this prerequisite
C) Submit an appeal to Green Business Certification Inc.
D) Ask the General Contractor to be more aggressive with recycling goals

US Green Building Council LEED-AP-BD+C Exam - Topic 10 Question 31 Discussion

Actual exam question for US Green Building Council's LEED-AP-BD+C exam
Question #: 31
Topic #: 10
[All LEED-AP-BD+C Questions]

A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?

Show Suggested Answer Hide Answer
Suggested Answer: A

. Revise the documentation and resubmit the form

If a project receives a review comment and technical advice on a prerequisite, it means that the documentation submitted was incomplete, inaccurate, or unclear, and that the project team needs to address the issues raised by the reviewer and provide additional information or clarification. The project team should revise the documentation and resubmit the form as part of the final review to demonstrate compliance with the prerequisite requirements. Abandoning meeting this prerequisite is not an option, as prerequisites are mandatory for LEED certification. Submitting an appeal to Green Business Certification Inc. is only applicable if the project team disagrees with the reviewer's decision or interpretation, and has additional evidence or arguments to support their claim. Asking the General Contractor to be more aggressive with recycling goals is not relevant to this prerequisite, as it does not address the documentation issue.


Contribute your Thoughts:

0/2000 characters
Lang
4 days ago
A) Revise the documentation and resubmit the form. That's the way to go!
upvoted 0 times
...
Tegan
9 days ago
Maybe asking the General Contractor to be more aggressive could help, but I feel like we should focus on the documentation first.
upvoted 0 times
...
Matt
14 days ago
I remember a similar question where we had to decide whether to appeal or revise. I think revising is usually the safer bet.
upvoted 0 times
...
Lashawna
19 days ago
I'm not entirely sure, but abandoning the prerequisite seems risky. We need to meet all requirements for certification, right?
upvoted 0 times
...
Tyra
25 days ago
I think the best option is to revise the documentation and resubmit. That seems like what we practiced in class.
upvoted 0 times
...

Save Cancel