Consider the following ADM phase objectives.

#

Objective

1

Determine whether an incremental approach is required, and if so identify Transition Architectures that will deliver continuous business value

2

Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D

3

Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan

4

Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders

Which two are objectives of ADM Phase F?

Show Suggested Answer Hide Answer
Suggested Answer: A

Comprehensive and Detailed In-Depth Explanation from Expert in Enterprise Architecture, guiding in TOGAF and ArchiMate:

ADM Phase F (Migration Planning) focuses on finalizing the Architecture Roadmap and Implementation and Migration Plan and ensuring they are viable, cost-effective, and clearly understood by decision-makers.

Phase F key objectives include:

Finalizing the Architecture Roadmap

Finalizing the Implementation and Migration Plan

Ensuring costs, benefits, risks, and dependencies of work packages and Transition Architectures are understood

Gaining approval for implementation sequencing and priorities

Why Option A is correct:

Objective 3 directly states the finalization of the Architecture Roadmap and supporting Implementation and Migration Plan, which is a core Phase F responsibility.

Objective 4 aligns with Phase F's requirement to ensure that business value, cost, and trade-offs are understood by stakeholders prior to implementation approval.

Why the other options are incorrect:

Objective 1 belongs primarily to Phase E (Opportunities and Solutions), where incremental delivery and Transition Architectures are identified.

Objective 2 also belongs to Phase E, where the initial complete Architecture Roadmap is generated from Phases B, C, and D outputs.

Authoritative TOGAF Reference:

TOGAF ADM Phase F -- Migration Planning

TOGAF Architecture Roadmap and Implementation and Migration Plan

============


Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel