Actual exam question for ScrumStudy's SMC exam
Question #: 116
Topic #: 3
[All SMC Questions]

You are the Scrum Master of the JKM Project and your Development Team has asked to change some rules about the duration of the Sprints. Which one of the following statements is a rule of Scrum that the team should follow when it comes to Sprint duration?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Carla
2 months ago
C makes the most sense, consistency is key!
upvoted 0 times
...
Ivan
2 months ago
Wait, are we really saying Sprints can change mid-project?
upvoted 0 times
...
Cassie
2 months ago
I think A could work too, but not ideal.
upvoted 0 times
...
Antonio
3 months ago
C is definitely the rule to follow!
upvoted 0 times
...
Bonita
3 months ago
B seems random, why Tuesday over Monday?
upvoted 0 times
...
Eloisa
3 months ago
I vaguely recall that once a Sprint duration is set, it shouldn't change. So, option C seems like the right choice, but I need to double-check that.
upvoted 0 times
...
Glory
3 months ago
I think the rule about starting Sprints on a Tuesday is just a suggestion, not a strict rule. So that makes me lean away from option B.
upvoted 0 times
...
Chau
4 months ago
I'm not entirely sure, but I feel like multiple teams can have different Sprint durations. Wasn't there a practice question about that?
upvoted 0 times
...
Kasandra
4 months ago
I remember discussing how Sprint duration should remain consistent once the project starts, so I think option C might be correct.
upvoted 0 times
...
Aimee
4 months ago
I remember learning that the Sprint duration is a key Scrum practice that should remain consistent throughout the project. I think option C is the right choice here.
upvoted 0 times
...
Carin
4 months ago
Wait, I thought Scrum teams could have different Sprint durations within the same project. I'm a bit confused now, but I'll review the Scrum principles to make sure.
upvoted 0 times
...
Bernadine
4 months ago
Okay, I've got this. The Scrum rules state that the Sprint duration should not change once the project begins. I'm confident that option C is the correct answer.
upvoted 0 times
...
Peggie
4 months ago
Hmm, I'm not sure about this. I know Scrum has specific guidelines for Sprint duration, but I can't recall the details off the top of my head.
upvoted 0 times
...
Laura
5 months ago
This is a tricky one. I'll need to think carefully about the Scrum rules to determine the right answer.
upvoted 0 times
...
Delfina
5 months ago
I think the rule is that the Sprint duration should not change once the project begins.
upvoted 0 times
...
Gussie
6 months ago
C) The Sprint duration should not change once the project begins. This is a fundamental rule of Scrum that the team must follow.
upvoted 0 times
Leatha
5 months ago
B) When possible, Sprints should start on a Tuesday rather than a Monday.
upvoted 0 times
...
Leonida
5 months ago
A) Multiple Scrum teams can have sprints of different duration in one project.
upvoted 0 times
...
...

Save Cancel