George is a Scrum Master on a project to develop a Course Management System and Leave ManagementSystem for Greyward University. He is maintaining an Impediment Log. Which one of the following statementsis NOT TRUE regarding Impediment Logs?
C) The Impediment Log must be shared with the stakeholders.
A) An impediment is any hindrance or hurdle that reduces the productivity of the Scrum Team.
B) Impediments can be internal or external to the team.
D) Impediments should be formally recorded by the Scrum Master in an Impediment Log.

ScrumStudy SMC Exam - Topic 2 Question 128 Discussion

Actual exam question for ScrumStudy's SMC exam
Question #: 128
Topic #: 2
[All SMC Questions]

George is a Scrum Master on a project to develop a Course Management System and Leave Management

System for Greyward University. He is maintaining an Impediment Log. Which one of the following statements

is NOT TRUE regarding Impediment Logs?

Show Suggested Answer Hide Answer
Suggested Answer: C