Question #: 8
Topic #: 1
[All Scrum Master Certified (SMC) Questions]

You are the Scrum Master for a project in a new Scrum environment. The Development Team is confused about their responsibilities in a Sprint. Of the following which one is not part of the Development Team's responsibilities?

Show Suggested Answer Hide Answer
Suggested Answer: B