ScrumStudy Exam SMC Topic 1 Question 78 Discussion

Actual exam question for ScrumStudy's SMC exam
Question #: 78
Topic #: 1
[All SMC Questions]

During a Scrum of Scrums Meeting certain Question:s are answered. Which of the following are the answered?

A) What has my team been working on since the last meeting?

B) What will my team do until the next meeting?

C) What were other teams counting on our team to finish that remains undone?

D) What is our team planning on doing that might affect other teams?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Raelene
21 days ago
Wait, there's a 'Scrum of Scrums'? Is that like a rugby match for Agile practitioners?
upvoted 0 times
...
Tommy
22 days ago
Option D seems the most comprehensive. I mean, who wouldn't want to know what other teams are depending on us for? Gotta keep those interdependencies in check!
upvoted 0 times
...
Marge
25 days ago
Haha, choice B is just too easy. Of course the team would want to know what they've been working on and what they plan to do next. I'm going with D, all of the above.
upvoted 0 times
Alfred
15 days ago
User 1: I agree, choice B is pretty straightforward.
upvoted 0 times
...
...
Erick
1 months ago
I was a bit unsure, but I'm going with C. A, B, and D. Seems like those cover all the key information that should be shared during the Scrum of Scrums.
upvoted 0 times
Samira
19 days ago
I agree, C includes what each team has been working on, what they will do next, and any potential impacts on other teams.
upvoted 0 times
...
Carman
1 months ago
I think C is the best choice. It covers all the important questions.
upvoted 0 times
...
...
Kathryn
2 months ago
Actually, I think it's all of the above, so option D.
upvoted 0 times
...
Elenor
2 months ago
I think the correct answer is D. All of the above. The Scrum of Scrums Meeting is designed to address all these questions to ensure cross-team coordination and visibility.
upvoted 0 times
Lashawnda
15 days ago
Yes, D is the best choice to ensure that all necessary information is shared during the Scrum of Scrums Meeting.
upvoted 0 times
...
Ludivina
18 days ago
I agree, D seems like the correct answer. It covers all the important aspects of team coordination.
upvoted 0 times
...
Georgiann
26 days ago
Yes, D is the best choice. It ensures that all teams are aligned and aware of each other's work.
upvoted 0 times
...
Shawn
28 days ago
I agree, D is the correct answer. It covers all the important aspects of team coordination.
upvoted 0 times
...
...
Sylvie
2 months ago
I believe it's A and B that are answered during the meeting.
upvoted 0 times
...
Kathryn
2 months ago
I think the answered questions in a Scrum of Scrums Meeting are C and D.
upvoted 0 times
...
Delila
2 months ago
Hmm, I see. I thought it was just C and D because those are the most important for coordination.
upvoted 0 times
...
Jennie
2 months ago
I believe it's all of the above, so option D.
upvoted 0 times
...
Delila
2 months ago
I think the answered questions are C and D.
upvoted 0 times
...