During a Scrum of Scrums Meeting certain Question:s are answered. Which of the following are the answered?
A) What has my team been working on since the last meeting?
B) What will my team do until the next meeting?
C) What were other teams counting on our team to finish that remains undone?
D) What is our team planning on doing that might affect other teams?