ScrumStudy SMC Exam - Topic 1 Question 60 Discussion

Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?
B) Facilitating identification of Change Requests by the Scrum Team and their assessment and prioritization by the Product Owner.
A) Eliminating all changes that may affect the quality of deliverables and processes
C) Providing requests for changes in a project.
D) Approving changes that are amended, removed, or added according to project requirements, and communicating the same to the Scrum Team.

ScrumStudy SMC Exam - Topic 1 Question 60 Discussion

Actual exam question for ScrumStudy's SMC exam
Question #: 60
Topic #: 1
[All SMC Questions]

Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Georgene
10 months ago
Wait, can the Scrum Master really eliminate changes? That seems off.
upvoted 0 times
...
Dominga
10 months ago
B makes sense, but isn't it the Product Owner's job to prioritize?
upvoted 0 times
...
Refugia
10 months ago
I thought the Scrum Master just facilitates, not approves changes.
upvoted 0 times
...
Jutta
10 months ago
I disagree, A seems more aligned with quality control.
upvoted 0 times
...
Thea
10 months ago
B is definitely the right choice!
upvoted 0 times
...
Marylyn
11 months ago
I’m a bit confused about option A, since eliminating changes doesn’t really align with the Agile mindset, right?
upvoted 0 times
...
Ardella
11 months ago
I feel like the Scrum Master shouldn't be the one approving changes, that seems more like the Product Owner's role.
upvoted 0 times
...
Nieves
11 months ago
I remember a practice question about the Scrum Master facilitating discussions, so maybe option B is correct?
upvoted 0 times
...
Nickole
11 months ago
I think the Scrum Master should help the team with change requests, but I'm not sure if that's the main responsibility.
upvoted 0 times
...
Billye
11 months ago
Hmm, this looks like a tricky one. I'll need to carefully analyze the code and the possible output options.
upvoted 0 times
...
Sheron
11 months ago
Hmm, I'm not sure which 7 time unit abbreviations are allowed. I'll have to think this through carefully.
upvoted 0 times
...
Anthony
11 months ago
I think one of the practice questions mentioned scaling capabilities, but I can't recall if it said anything about a maximum number of nodes like 16. Was that specific?
upvoted 0 times
...

Save Cancel