ScrumStudy SMC Exam - Topic 1 Question 60 Discussion
Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?
B) Facilitating identification of Change Requests by the Scrum Team and their assessment and prioritization
by the Product Owner.
A) Eliminating all changes that may affect the quality of deliverables and processes
C) Providing requests for changes in a project.
D) Approving changes that are amended, removed, or added according to project requirements, and
communicating the same to the Scrum Team.