On a hydroelectric power project, damage to life and property due to floods and landslides has been identified

as a potential risk. Which of the following Risk Assessment Techniques can be used by the Scrum Team to

assess the potential risk, and its impact on project objectives?

Show Suggested Answer Hide Answer
Suggested Answer: A