ScrumStudy SMC Exam - Topic 1 Question 58 Discussion

Actual exam question for ScrumStudy's SMC exam
Question #: 58
Topic #: 1
[All SMC Questions]

On a hydroelectric power project, damage to life and property due to floods and landslides has been identified

as a potential risk. Which of the following Risk Assessment Techniques can be used by the Scrum Team to

assess the potential risk, and its impact on project objectives?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Junita
4 months ago
Wait, can these really predict floods and landslides? Sounds risky!
upvoted 0 times
...
Bulah
4 months ago
Expected Monetary Value is a solid choice too!
upvoted 0 times
...
Eva
4 months ago
Pareto Analysis? Not sure it fits here.
upvoted 0 times
...
Sherly
4 months ago
I think Probability Trees might be better for complex scenarios.
upvoted 0 times
...
Yuriko
4 months ago
Probability Impact Grid is super useful for this!
upvoted 0 times
...
Maryanne
5 months ago
Expected Monetary Value could be useful, but I feel like it’s more about quantifying risks rather than assessing their impact directly.
upvoted 0 times
...
Clare
5 months ago
Pareto Analysis sounds familiar, but I can't recall if it's really used for this kind of risk assessment.
upvoted 0 times
...
Dominque
5 months ago
I'm not entirely sure, but I think Probability Trees might be more about decision-making rather than just assessing risks.
upvoted 0 times
...
Ellsworth
5 months ago
I remember studying the Probability Impact Grid; it seems like a good fit for assessing risks like floods and landslides.
upvoted 0 times
...
Tess
5 months ago
Hmm, I'm a bit unsure about this one. The question mentions licensing fees, so I wonder if the number of customers using the software could also be a key consideration. I'll have to think this through carefully.
upvoted 0 times
...
Stephanie
5 months ago
I've got a good feeling about this one. The Create Security Incident action should raise a new security incident, but I'm not sure if it's automatically resolved or just displayed to the agent.
upvoted 0 times
...

Save Cancel