ScrumStudy SMC Exam - Topic 4 Question 124 Discussion
Which of the following is NOT an objective of a Retrospect Sprint Meeting?
C) Identify new product features
A) Identify process improvements
B) Identify best practices
D) Identify process problems and bottlenecks
:
Primary objectives of the meeting are to identify three specific things:
Things the team needs to keep doing: best practices
Things the team needs to begin doing: process improvements
Things the team needs to stop doing: process problems and bottlenecks
These areas are discussed and a list of Agreed Actionable Improvements is created.