ScrumStudy SMC Exam - Topic 1 Question 40 Discussion

Actual exam question for ScrumStudy's SMC exam
Question #: 40
Topic #: 1
[All SMC Questions]

Van is the Product Owner for the JK Project. He's asked you for help in prioritizing the items in the product backlog. How should Van ordered the user stories in the Product Backlog?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Nelida
4 months ago
Totally agree, priority first!
upvoted 0 times
...
Callie
4 months ago
Wait, why would you put risky items at the bottom?
upvoted 0 times
...
Jaleesa
4 months ago
Easiest items first? That seems off to me.
upvoted 0 times
...
Slyvia
4 months ago
I think cost should matter too, though.
upvoted 0 times
...
Cristal
4 months ago
Higher priority stories should definitely be on top!
upvoted 0 times
...
Chau
5 months ago
I recall that risky items should be addressed early, but I'm not sure if they should be at the bottom. D feels a bit confusing.
upvoted 0 times
...
Daniela
5 months ago
I'm not entirely sure, but I feel like cost shouldn't be the main factor for prioritization. Maybe B is wrong?
upvoted 0 times
...
Louvenia
5 months ago
I remember that prioritizing user stories should focus on value to the customer, so I think A makes sense.
upvoted 0 times
...
Earnestine
5 months ago
I practiced a similar question, and I think the easiest items might not always be the most valuable. So C seems off to me.
upvoted 0 times
...
Helene
5 months ago
Okay, let's see. I know Advanced ACLs have more parameters than a standard ACL, so I'll need to consider which one is not used.
upvoted 0 times
...
Ona
5 months ago
I'm a bit confused by the different sharing models mentioned. Does the Private sharing model for External users impact the solution we should choose?
upvoted 0 times
...

Save Cancel