Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to

your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories

committed to for the current Sprint because the customer has changed a critical business requirement. Which

one of the following statements presents the best solution for such a situation?

Show Suggested Answer Hide Answer
Suggested Answer: B