Scenario C: Dependencies and Product Backlog items
During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams
identify many dependencies. This makes it hard for them to choose the work they could pull
into their individual teams for the next Sprint. No matter how they reorganize the Product
Backlog items, they continually find more or new dependencies.
What techniques could help this Nexus manage their dependencies effectively?
(choose the best two answers)
Suggested Answer: B, D
Get Premium SPS Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
17 comments · newest first
RO
Rosalind
10 months ago
B seems risky, mixing team members could create more chaos.
BE
Belen
11 months ago
Surprised they didn't mention better communication between teams!
LU
Lucina
11 months ago
D could help, but it might not solve all dependency issues.
OL
Olga
11 months ago
Totally disagree with C, extending the Sprint just delays the inevitable.
MO
Mollie
11 months ago
A is a solid choice, tackling dependencies upfront makes sense.
JA
Jacklyn
12 months ago
Reorganizing team members sounds like it could work, but it might disrupt team dynamics. I’m torn on that one!
EL
Elenor
12 months ago
I feel like the Nexus Integration Team completing the dependent work ahead of the Sprint could be a viable option, but it seems risky to rely solely on that.
RO
Royal
12 months ago
I think extending the Sprint might just lead to more issues down the line. We practiced a similar question where time management was crucial.
BE
Benton
1 year ago
I remember we discussed how reorganizing the Product Backlog could help with dependencies, but I'm not sure if it's the best approach in this scenario.
JE
Jeannetta
1 year ago
The Nexus Integration Team doing the dependent work upfront makes a lot of sense to me. That way the individual teams can focus on their own work during the Sprint.
GL
Glen
1 year ago
I'm a bit confused on the best approach here. There are a few options, but I'm not sure which would be the most effective. Guess I'll have to think it through carefully.
AM
Amie
1 year ago
Extending the Sprint seems like it could just kick the can down the road. We need a more proactive approach to tackle these dependencies head-on.
LI
Linsey
1 year ago
Hmm, reorganizing the teams to eliminate cross-team dependencies sounds promising, but that could be a big disruption. Reordering the backlog might be a simpler solution.
AL
Alexis
1 year ago
This is a tricky one. Lots of dependencies to manage across 9 teams. I'm thinking the Nexus Integration Team could be key to getting ahead of the dependencies.
ME
Merissa
1 year ago
The Legal Hold Defensibility Report sounds like it could be the right one, since it's specifically mentioned in the court order details. I'll double-check that to be sure.
KA
Kayleigh
1 year ago
This question seems straightforward. I'm pretty confident I can get this one right.
MI
Miriam
1 year ago
I think the URL modification might be a key point here. Does it really have to end with ?limit=10? That feels right, but I'm not entirely confident.