Scrum Exam PSPO-I Topic 1 Question 3 Discussion

Actual exam question for Scrum's Professional Scrum Product Owner I exam
Question #: 3
Topic #: 1
[All Professional Scrum Product Owner I Questions]

True or False: The Product Owner must write all of the Product Backlog items (e.g., user stories, requirements, etc.) on the Product Backlog before handing them over to the Scrum Team.

Show Suggested Answer Hide Answer
Suggested Answer: B

It is not true that the Product Owner must write all of the Product Backlog items (e.g. user stories, requirements, etc.) on the Product Backlog before handing them over to the Scrum Team. This is because:

The Product Backlog is an emergent, ordered list of what is needed to improve the product. It is never complete and constantly changes to reflect the needs and desires of the customers, users, and stakeholders.

The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. They are responsible for identifying and articulating the Product Goal, which is a long-term objective for the product that guides all the activities of the Scrum Team.

The Product Owner is also accountable for managing the Product Backlog items effectively. They must ensure that they are transparent, visible, and understood by everyone who needs to work on them. They must also collaborate with the Developers and stakeholders to refine, order, and prioritize them based on value and impact.

The Product Owner does not need to write all of the Product Backlog items by themselves or before handing them over to the Scrum Team. They can involve others in creating or contributing to them, such as customers, users, stakeholders, or Developers. They can also add or modify them at any time during the product development process, as long as they are clear and ready for selection in Sprint Planning.


[Scrum Guide], page 6, section ''Product Owner''

[Scrum Guide], page 11, section ''Product Backlog''

[Scrum Guide], page 10, section ''Product Goal''

[Scrum Guide], page 12, section ''Product Backlog Refinement''

[Scrum Guide], page 14, section ''Sprint Planning''