You are the Scrum Master for three Scrum Teams working on the same product. There is a single Product Backlog that all three Scrum Teams select from. Management is eager to improve the productivity of the teams and wants to standardize velocity across all three teams so that they can see how each team is delivering value. When responding to management, which two statements are appropriate?
(choose the best two answers)
C: Velocity has no direct relationship with value. This is a true statement, as velocity is a measure of the amount of work done by a Scrum Team in a Sprint, not the value or quality of that work. Velocity can vary depending on many factors, such as the size, complexity, and priority of the Product Backlog items, the skills and experience of the Developers, the Definition of Done, and the Sprint length. Therefore, velocity is not a reliable indicator of value creation or team performance.
D: Velocity is the amount of business functionality that a Scrum Team creates in a Sprint. It is unique to that team and used as an input to Sprint Planning. This is a true statement, as velocity is a team-specific metric that reflects how much business functionality the Scrum Team can deliver in a Sprint. Velocity can help the Scrum Team to forecast how many Product Backlog items they can select for the next Sprint, based on their past performance and current capacity. However, velocity is not a goal or a target for the Scrum Team, and it should not be compared across teams.
Professional Scrum Master II Course, page 15: ''Velocity is a measure of how much work a team can complete in a given time period. It is usually expressed in terms of story points or function points per Sprint.''
Professional Scrum Master II Course, page 16: ''Velocity is not a measure of value or quality. It does not tell us anything about the usefulness, usability, or desirability of the product increment.''
Professional Scrum Master II Course, page 17: ''Velocity is unique to each team and depends on many factors, such as the size and complexity of the work items, the skills and experience of the team members, the definition of done, and the length of the Sprint.''
Professional Scrum Master II Course, page 18: ''Velocity can be used as an input for Sprint Planning, to help the team forecast how much work they can realistically accomplish in the next Sprint. However, velocity is not a goal or a target for the team, and it should not be used to compare or evaluate teams.''
Sheron
2 months agoAn
2 months agoJarvis
3 months agoTalia
3 months agoMarjory
3 months agoGraham
3 months agoNan
4 months agoCassi
4 months agoCarli
4 months agoOmega
4 months agoLucina
4 months agoCatalina
4 months agoEun
5 months agoJulianna
6 months agoOna
5 months agoBrande
5 months agoFrance
5 months agoEmilio
7 months agoGaston
7 months agoBasilia
5 months agoSharee
6 months agoYan
7 months agoDona
6 months agoHannah
7 months agoSkye
7 months agoCrista
7 months ago