Marian is a product Owner working on a Scrum Team on a new release for her product. Based on the average velocity of the previous release Marian estimated the project to take seven Sprints. Average velocity In the previous release was thirteen completed units of work per Sprint Development is three Sprints underway, with tour more Sprints to go until the release.
Product Backlog has been stable.
Over the first three Sprints, the Developers report their average velocity is nine, while not having fully tested all the delivered functionality. The Developers estimate that the unfinished testing would have required of a Sprints time. The Developers believe that the required
velocity of thirteen is within their reach. What is the most effective way to recover?
(choose the best answer)
A. The Developers set the open work aside to be performed in one or more release Sprints. They remind Marian to find funding for enough Release Sprints in which this remaining work can be done. up to one release Sprint per three development Sprints may be required, It is Marian's responsibility to inform users and stakeholders Of the impact on the release date.
B. Transparency needs to be restored by addng the undone work to the Product Backlog. The Developers must figure out a way to deliver in the upcoming Sprints a velocity of not only 13 units of new work, but also two additional points to catch up undone work. It is the Scrum Master's duty to assess whether such repair is possible. If not, the Scrum Master initiates a restart with a more reliable team Or cancels the project. The Scrum Master will have to inform Product Owner and the stakeholders.
The most effective way to recover is to restore transparency and trust by informing the Product Owner that the progress she has perceived to date is not correct.The Increment is not releasable because it does not meet the Definition of Done12, which is a shared understanding of what it means for work to be complete12. The Developers should give the Product Owner their estimate of the effort it would take to get the past work done, and suggest doing that work first before proceeding with new features.This way, the Developers can ensure that they deliver a valuable, useful, and potentially releasable Increment every Sprint12. The Developers should also re-estimate the effort to complete the remaining backlog, including all testing, and communicate any changes or risks to the Product Owner.In the end, it is the Product Owner's call to continue the project or to cancel it, based on the value and feasibility of the product12.
Some reasons why the other options are not correct are:
A: The Developers set the open work aside to be performed in one or more release Sprints. They remind Marian to find funding for enough Release Sprints in which this remaining work can be done. This option is not correct because it violates the Scrum framework and the Scrum values.The Scrum framework does not prescribe any release Sprints or separate phases for testing or integration12.The Scrum values include commitment, focus, openness, respect, and courage12. The Developers should commit to delivering a potentially releasable Increment every Sprint, not postpone or hide their undone work. The Developers should focus on creating value for the customers and users, not on meeting artificial deadlines or metrics. The Developers should be open and honest about their progress and challenges, not mislead or deceive the Product Owner.The Developers should respect the Product Owner's authority and accountability for maximizing the value of the product and the work of the Developers12, not shift the responsibility or blame to them. The Developers should have the courage to face their problems and seek help, not avoid or ignore them.
B: Transparency needs to be restored by adding the undone work to the Product Backlog. The Developers must figure out a way to deliver in the upcoming Sprints a velocity of not only 13 units of new work, but also two additional points to catch up undone work. It is the Scrum Master's duty to assess whether such repair is possible. If not, the Scrum Master initiates a restart with a more reliable team or cancels the project. The Scrum Master will have to inform Product Owner and the stakeholders. This option is not correct because it violates the Scrum framework and the Scrum roles.The Scrum framework does not prescribe any velocity or points as measures of progress or success12.The Scrum roles include Product Owner, Scrum Master, and Developers12.The Product Owner is accountable for maximizing the value of the product and the work of the Developers12, not for tracking or controlling their velocity or points.The Scrum Master is accountable for establishing Scrum as defined in the Scrum Guide1, causing change that increases the productivity of the Scrum Team1, and working with other Scrum Masters to increase the effectiveness of the application of Scrum in the organization1, not for assessing or judging the performance of the Developers or initiating a restart or cancellation of the project.The Developers are accountable for creating a valuable, useful, and potentially releasable Increment every Sprint12, not for meeting a predetermined velocity or points target.
C: In the next Sprints, the Developers keep making sure that all of the selected scope per Sprint is as done as possible, at least at the past level of 90%. In every Sprint the undone work of the previous Sprint is estimated and added to the Sprint Backlog. It comes on top of the expected forecast of 13 units, so it does not mess up progress on the product Backlog. This option is not correct because it violates the Scrum framework and the Scrum values.The Scrum framework requires that each Sprint delivers a potentially releasable Increment that meets the Definition of Done12, not a partially done or incomplete product that accumulates technical debt or quality issues.The Scrum values include commitment, focus, openness, respect, and courage12. The Developers should commit to delivering a potentially releasable Increment every Sprint, not compromise on quality or value. The Developers should focus on creating value for the customers and users, not on meeting artificial deadlines or metrics. The Developers should be open and honest about their progress and challenges, not hide or ignore their undone work.The Developers should respect the Product Owner's authority and accountability for maximizing the value of the product and the work of the Developers12, not burden them with additional work or risk. The Developers should have the courage to face their problems and seek help, not avoid or ignore them.
What is an Increment? | Scrum.org
What is a Product Increment? | Scrum.org
In the Daily Scrum, the Product Owner applauds every Developer who moves a Sprint Backlog item to completion. The Product Owner wants to encourage the Developers to make progress visible on the burn-down chart. Select the two best options for the Scrum Master to take.
(choose the best two answers)
This is a good option because the Scrum Master's role is to help the Scrum Team understand and apply the Scrum framework and its principles12.The Scrum Master should also facilitate and enable the team's self-organization and collaboration12.By coaching the Scrum Team, the Scrum Master can help them realize that the Daily Scrum is not a status update or a performance review, but a time to inspect and adapt their progress toward the Sprint Goal3. D. Tell the Product Owner your concerns about how his behavior may impact the Developers, and ask him to stop attending the Daily Scrum for some time.
This is another good option because the Scrum Master's role is to protect the Scrum Team from external interference and distractions12.The Scrum Master should also coach the Product Owner on how to maximize the value of the product and collaborate effectively with the Developers12. By telling the Product Owner your concerns, you can help him understand that his behavior may create pressure, dependency, or resentment among the Developers, which can harm their motivation, creativity, and autonomy . By asking him to stop attending the Daily Scrum for some time, you can give the Developers some space to self-manage their work and communication.
True or False: Using Scrum ensures that adding more resources to a project proportionally increases the value delivered.
Using Scrum does not ensure that adding more resources to a project proportionally increases the value delivered.In fact, adding more resources may have the opposite effect, as it can introduce more complexity, communication overhead, coordination challenges, and integration issues12.Scrum values quality over quantity, and focuses on delivering the most valuable and feasible outcomes in a given timebox3.Scrum also encourages teams to be self-organizing and cross-functional, which means that they can work autonomously and collaboratively without relying on external resources or dependencies3.
Towards the end of Sprint Planning, the Product Owner and the Developers have not been able to reach a clear, mutual understanding about the highest order Product Backlog items. Because of this, the Developers could not figure out how many Product Backlog items they could forecast for the upcoming Sprint. The Product Owner did make it clear what business objective he is hoping to achieve with this Sprint. Which of the following two actions would you support?
(choose the best two answers)
A) They discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur. This is a good action to take, as it shows that the Scrum Team is willing to inspect and adapt their process and improve their collaboration and communication. The Sprint Retrospective is an opportunity for the Scrum Team to identify the root causes of the problem and create a plan for implementing improvements in the next Sprint.
D) The Developers forecast the most likely Product Backlog items to meet the business objective and create a Sprint Backlog based on a likely initial design and plan. Once the timebox for the Sprint Planning event is over, they start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint. This is also a good action to take, as it shows that the Scrum Team is flexible and adaptive, and does not let uncertainty or ambiguity prevent them from delivering value. The Developers can use the Sprint Goal as a guide to select and refine the Product Backlog items during the Sprint, and collaborate with the Product Owner to ensure that they are meeting the expectations and needs of the stakeholders.
The Scrum Guide, section 3.1 (The Sprint), page 8
The Scrum Guide, section 3.3 (The Sprint Goal), page 9
The Scrum Guide, section 3.5 (The Sprint Planning), page 10
The Scrum Guide, section 3.7 (The Sprint Retrospective), page 12
The Scrum Master Learning Path, module 2 (The Scrum Framework), lesson 2 (The Sprint), lesson 3 (The Sprint Goal), lesson 4 (Sprint Planning) and lesson 6 (The Sprint Retrospective)
During Sprint Planning, Developers work with the Product Owner to create a forecast for the Sprint. A forecast is a selection of Product Backlog items that the Developers believe are possible to get done by the end of the Sprint. Select two things that explain what done means.
(choose the best two answers)
Done means that the Increment is in a usable condition and meets the Scrum Team's Definition of Done. The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product. The Definition of Done creates transparency by providing everyone a shared understanding of what work was completed as part of the Increment. Having an Increment that could be released to end users means that it is potentially releasable, which is one of the goals of Scrum. All work performed meets the Definition of Done means that the Developers have ensured that every Product Backlog item selected for the Sprint conforms to the agreed quality standards.
The Scrum Guide, November 2020, p. 10-11
What is a Definition of Done?, Scrum.org, accessed on September 30, 2023
DONE Understanding Of The Definition Of 'Done'', Scrum.org, December 16, 2019
Lisa Hernandez
15 hours agoHeather Peterson
22 days agoTimothy Baker
1 month agoBrian Sanchez
2 months agoMichael Walker
2 months agoPatricia Parker
3 months agoJeffrey Martinez
2 months agoDeborah Rodriguez
2 months agoCrystal Hall
2 months agoRichard Brown
2 months agoDennis Cook
2 months agoBrett
3 months agoLisbeth
3 months agoMicaela
4 months agoLeah
4 months agoWilburn
4 months agoLizbeth
4 months agoLizette
5 months agoHerminia
5 months agoJutta
5 months agoKami
5 months agoJoni
6 months agoCarrol
6 months agoMyrtie
6 months agoMaxima
6 months agoDonte
7 months agoTyra
7 months agoRoy
7 months agoAngelyn
7 months agoNathalie
8 months agoDorothy
8 months agoAdelle
8 months agoDenise
8 months agoGladis
9 months agoLili
9 months agoKiera
9 months agoHillary
9 months agoPamella
10 months agoHelga
10 months agoNoah
10 months agoMarge
1 year agoBelen
1 year agoCarmela
1 year agoRodrigo
1 year agoFabiola
1 year agoJacquelyne
1 year agoAretha
1 year agoTammara
2 years agoLorenza
2 years agoDelsie
2 years agoOlive
2 years agoAudra
2 years agoJanae
2 years agoJess
2 years agoCristen
2 years agoTricia
2 years agoYesenia
2 years agoJoni
2 years agoJustine
2 years agoMicah
2 years agoLashawn
2 years agoMi
2 years agoGene
2 years agoIlene
2 years agoAlethea
2 years agoIsadora
2 years ago