A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation?

(Choose two.)

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Skye
4 days ago
I agree, the first two options seem like the best approach. Bringing in all the project managers might just add more chaos to the situation.
upvoted 0 times
...
Detra
12 days ago
Adding each open impediment to the Product Backlog could help track them better.
upvoted 0 times
...
Laurel
15 days ago
I agree with Corinne. Prioritizing the list and working on them in order is also crucial.
upvoted 0 times
...
Kristel
15 days ago
Discussing the impediments with the Development Team is a must, they're the ones who know the issues best. Prioritizing and working on them in order also makes sense.
upvoted 0 times
Rima
1 days ago
A: We should definitely discuss the impediments with the Development Team.
upvoted 0 times
...
...
Corinne
18 days ago
I think A) Discuss the impediments with the Development Team is important.