Scrum Exam PSM-I Topic 4 Question 70 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 70
Topic #: 4
[All PSM-I Questions]

Who is accountable for managing the progress ot work during a Sprint?

(choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: A, B

The best two answers are A and B. As a Scrum Team, prioritizing the list and working on them in order is a good technique to tackle the impediments. This way, the team can focus on the most urgent and important issues first and avoid being overwhelmed by the number of impediments. The Scrum Master discusses the impediments with the Scrum Team is also a helpful technique, as it allows the team to share their perspectives, identify the root causes, and come up with possible solutions. The Scrum Master can also coach the team on how to remove or prevent impediments in the future.


Contribute your Thoughts:

Viki
2 months ago
Definitely C) The Scrum Master. They're the ones keeping the team focused and making sure the Sprint goals are met. Unless the Scrum Master is the coffee machine, in which case I have some concerns.
upvoted 0 times
...
Janae
2 months ago
The most junior member of the team? Really? That's just asking for trouble. Might as well put the coffee machine in charge while we're at it.
upvoted 0 times
Ira
19 days ago
The most junior member of the team? Really? That's just asking for trouble. Might as well put the coffee machine in charge while we're at it.
upvoted 0 times
...
Annice
20 days ago
C) The Scrum Master.
upvoted 0 times
...
Kyoko
1 months ago
B) The Developers.
upvoted 0 times
...
Graciela
1 months ago
A) The Product Owner.
upvoted 0 times
...
...
Jennifer
2 months ago
C) The Scrum Master is the right answer. That's their primary role, to facilitate the Sprint and ensure the team is on track.
upvoted 0 times
Maxima
1 months ago
C) The Scrum Master.
upvoted 0 times
...
Germaine
1 months ago
B) The Developers.
upvoted 0 times
...
Torie
1 months ago
A) The Product Owner.
upvoted 0 times
...
...
Sage
2 months ago
I think the correct answer is B) The Developers. They are the ones actually doing the work and should be accountable for managing the progress.
upvoted 0 times
Devora
23 days ago
The Product Owner also plays a role in managing the progress of work during a Sprint.
upvoted 0 times
...
Chaya
24 days ago
Actually, it is the Scrum Master who is accountable for managing the progress of work during a Sprint.
upvoted 0 times
...
Kristeen
1 months ago
I agree, the Developers are responsible for managing the progress of work during a Sprint.
upvoted 0 times
...
...
Maurine
3 months ago
The Scrum Master is responsible for managing the progress during a Sprint, not the Product Owner or the Developers. The most junior member of the team definitely doesn't have that responsibility.
upvoted 0 times
Ruthann
13 days ago
Definitely not. The most junior member of the team does not have that responsibility.
upvoted 0 times
...
Mattie
14 days ago
D) The most junior member of the team.
upvoted 0 times
...
Janine
15 days ago
The Developers are not responsible for managing the progress during a Sprint.
upvoted 0 times
...
Clarence
16 days ago
B) The Developers.
upvoted 0 times
...
Carey
18 days ago
No, the Product Owner is not accountable for managing the progress during a Sprint.
upvoted 0 times
...
Huey
23 days ago
A) The Product Owner.
upvoted 0 times
...
Junita
24 days ago
That's correct. The Scrum Master is responsible for managing the progress during a Sprint.
upvoted 0 times
...
Remona
1 months ago
C) The Scrum Master.
upvoted 0 times
...
...
Vanna
3 months ago
A) The Product Owner. They have the overall vision for the project.
upvoted 0 times
...
Starr
3 months ago
B) The Developers. They are the ones actually doing the work.
upvoted 0 times
...
Portia
3 months ago
C) The Scrum Master. They are responsible for ensuring the team is on track.
upvoted 0 times
...
Dominic
3 months ago
B) The Developers. They are the ones actually doing the work and should be managing their own progress.
upvoted 0 times
...
Quentin
3 months ago
A) The Product Owner. They have the overall vision for the product and can provide guidance on priorities.
upvoted 0 times
...
Raylene
3 months ago
C) The Scrum Master. They are responsible for ensuring the team is on track and removing any obstacles.
upvoted 0 times
...

Save Cancel