Scrum PSM-I Exam - Topic 4 Question 42 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 42
Topic #: 4
[All PSM-I Questions]

Which statement best describes the Sprint Backlog as the output ot the Sprint Planning?

(choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Nichelle
4 months ago
Nah, it's more about the Developers' plan than anything else.
upvoted 0 times
...
Basilia
4 months ago
Every item should have a designated owner, right?
upvoted 0 times
...
Chanel
4 months ago
Surprised that people think it's a complete list!
upvoted 0 times
...
Yuonne
4 months ago
I thought the Product Owner ordered it?
upvoted 0 times
...
Joseph
4 months ago
It's definitely the Developers plan for the Sprint.
upvoted 0 times
...
Fidelia
5 months ago
I thought every item had a designated owner, but now I'm questioning if that's really how it works in the Sprint Backlog.
upvoted 0 times
...
Blair
5 months ago
I feel like I saw a question similar to this in our practice exam, and it emphasized that the Sprint Backlog is the Developers' plan.
upvoted 0 times
...
Melissa
5 months ago
I remember something about the Product Owner ordering items, but I don't think that's what the Sprint Backlog is specifically about.
upvoted 0 times
...
Richelle
5 months ago
I think the Sprint Backlog is more about the Developers' plan for the Sprint, but I'm not entirely sure if that's the best answer.
upvoted 0 times
...
Alana
5 months ago
I'm pretty confident that the answer is A. Assessment Task Plan. That seems to be the most appropriate option for creating an Action Plan in the Consumer Goods Cloud context.
upvoted 0 times
...
Yesenia
5 months ago
Protecting against zero-day attacks can be really challenging, but I know there are some strategies like keeping software updated and using robust security measures.
upvoted 0 times
...
Heike
10 months ago
I agree with Lelia. The Sprint Backlog is the Developers' plan for the Sprint, which they create collaboratively during the Sprint Planning meeting.
upvoted 0 times
Maurine
9 months ago
C) Each task is estimated in hours.
upvoted 0 times
...
Raylene
9 months ago
B) It is ordered by the Product Owner.
upvoted 0 times
...
Percy
9 months ago
A) Every item has a designated owner.
upvoted 0 times
...
...
Kasandra
10 months ago
Haha, the answer is definitely not A. Designating owners for every item in the Sprint Backlog? That's just too much micromanagement!
upvoted 0 times
Bettina
9 months ago
D) It is the Developers plan for the Sprint
upvoted 0 times
...
Cathern
9 months ago
C) Each task is estimated in hours.
upvoted 0 times
...
Alisha
9 months ago
B) It is ordered by the Product Owner.
upvoted 0 times
...
...
Camellia
10 months ago
I'm not sure about that. I think option E is correct - the Sprint Backlog is a complete list of all the work to be done in a Sprint.
upvoted 0 times
Ezekiel
8 months ago
Yes, that's right. Each task is estimated in hours and it is the plan for the Sprint.
upvoted 0 times
...
Diego
8 months ago
Oh, I see. So the correct answer is D) It is the Developers plan for the Sprint.
upvoted 0 times
...
Paris
8 months ago
Actually, the Sprint Backlog is the Developers plan for the Sprint.
upvoted 0 times
...
Paola
8 months ago
I think option E is correct - the Sprint Backlog is a complete list of all the work to be done in a Sprint.
upvoted 0 times
...
Lili
9 months ago
I agree with you, option E makes the most sense for the Sprint Backlog.
upvoted 0 times
...
Janey
9 months ago
I believe it's option A - every item has a designated owner in the Sprint Backlog.
upvoted 0 times
...
Winfred
9 months ago
I think it's actually option D - the Sprint Backlog is the Developers plan for the Sprint.
upvoted 0 times
...
Mari
10 months ago
Option E is correct - the Sprint Backlog is a complete list of all the work to be done in a Sprint.
upvoted 0 times
...
...
Lelia
10 months ago
I think option D is the best answer. The Sprint Backlog is the Developers' plan for the Sprint, which they create during the Sprint Planning.
upvoted 0 times
Minna
10 months ago
Actually, I think option E is the best answer. It is a complete list of all work to be done in a Sprint.
upvoted 0 times
...
Maile
10 months ago
I agree, option D is correct. The Sprint Backlog is the Developers' plan for the Sprint.
upvoted 0 times
...
...
Jonelle
10 months ago
Hmm, that makes sense too. Maybe we should review the material again before the exam.
upvoted 0 times
...
Simona
10 months ago
I disagree, I believe the answer is E) It is a complete list of all work to be done in a Sprint.
upvoted 0 times
...
Jonelle
11 months ago
I think the answer is D) It is the Developers plan for the Sprint.
upvoted 0 times
...