New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Scrum PSM-I Exam - Topic 3 Question 45 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 45
Topic #: 3
[All PSM-I Questions]

True or False: Multiple scrum Teams working on the same product must have the same Sprint start date.

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Carlota
4 months ago
This seems odd, why wouldn't they sync up?
upvoted 0 times
...
Ariel
4 months ago
Nope, just need to coordinate on goals.
upvoted 0 times
...
Leonida
4 months ago
Wait, really? I thought they had to align.
upvoted 0 times
...
Carma
4 months ago
Totally agree, flexibility is key!
upvoted 0 times
...
Lavonna
4 months ago
It's False! Teams can have different start dates.
upvoted 0 times
...
Aaron
5 months ago
I’m leaning towards false. I think it’s more about the teams being able to work at their own pace while still collaborating effectively.
upvoted 0 times
...
Lyndia
5 months ago
I feel like it could go either way. It makes sense for alignment, but I also recall something about flexibility in Scrum.
upvoted 0 times
...
Margart
5 months ago
I remember a practice question about this, and I think it was false. Different teams can have different start dates, right?
upvoted 0 times
...
Jaime
5 months ago
I think it's true because having the same Sprint start date helps with coordination, but I'm not entirely sure.
upvoted 0 times
...
Marleen
5 months ago
This one seems pretty straightforward. Loss provisioning is meant to cover unexpected losses, so I'll go with option A.
upvoted 0 times
...
Yuriko
5 months ago
Hmm, the question mentions some specific logging categories, but I'm not sure how that relates to the code snippet. I'll have to analyze that carefully.
upvoted 0 times
...
Haydee
5 months ago
Okay, I've got a strategy here. I'll go through each statement, check the syntax, and make notes on which ones I think will execute successfully.
upvoted 0 times
...
Vanna
5 months ago
I'm not totally sure about this one. The wording of the question and the rule itself seem a bit ambiguous to me. I'll need to think it through carefully to make sure I don't miss anything.
upvoted 0 times
...
Irma
9 months ago
Wait, is this a trick question? *scratches head* I better review the Scrum principles again before answering this one.
upvoted 0 times
Coral
8 months ago
That's correct! Each Scrum Team can have its own Sprint start date to better suit their needs.
upvoted 0 times
...
Gail
8 months ago
I think it's false because each Scrum Team can have its own Sprint start date.
upvoted 0 times
...
Christene
8 months ago
B) False
upvoted 0 times
...
Timothy
8 months ago
A) True
upvoted 0 times
...
...
Myong
9 months ago
True? False? Who cares, as long as the Scrum teams are delivering value, right? *laughs* Just kidding, gotta get this one right for the exam.
upvoted 0 times
...
Delila
9 months ago
False, for sure. Forcing all Scrum teams to have the same Sprint start date would be way too rigid and could create unnecessary coordination headaches.
upvoted 0 times
...
Ashlyn
10 months ago
The answer has to be False. Each Scrum team should have the flexibility to set their own Sprint schedule based on their work and dependencies.
upvoted 0 times
Ligia
8 months ago
False. It's important for teams to have flexibility in setting their Sprint start date.
upvoted 0 times
...
Cassandra
9 months ago
True. No, that's incorrect. Each team can have their own schedule.
upvoted 0 times
...
Toshia
9 months ago
False. Each Scrum team can have their own Sprint start date.
upvoted 0 times
...
...
Chandra
10 months ago
Hmm, this is a tricky one. I've heard that it can be beneficial to have the same Sprint start date, but I'm not sure if it's a strict requirement. Better double-check the Scrum guide on this one.
upvoted 0 times
Josefa
8 months ago
A) True
upvoted 0 times
...
Olen
8 months ago
I think it's False, each team can have their own Sprint start date.
upvoted 0 times
...
Gwenn
8 months ago
B) False
upvoted 0 times
...
Sue
9 months ago
A) True
upvoted 0 times
...
...
Carolynn
10 months ago
I'm pretty sure the answer is False. It doesn't make sense for all Scrum teams to have the same Sprint start date if they're working on the same product.
upvoted 0 times
Justine
8 months ago
True, each Scrum Team should have their own Sprint start date based on their own needs and priorities.
upvoted 0 times
...
Norah
8 months ago
I agree, it wouldn't be practical for all teams to start their sprints on the same day.
upvoted 0 times
...
Caitlin
8 months ago
B) False
upvoted 0 times
...
Venita
8 months ago
A) True
upvoted 0 times
...
Justine
8 months ago
True, each team should have their own sprint start date based on their own needs and priorities.
upvoted 0 times
...
Emily
9 months ago
I agree, it wouldn't be practical for all teams to start their sprints on the same day.
upvoted 0 times
...
Giovanna
9 months ago
B) False
upvoted 0 times
...
Alecia
9 months ago
B) False
upvoted 0 times
...
Antonio
9 months ago
I agree, it wouldn't make sense for all teams to start their sprints on the same date.
upvoted 0 times
...
Laine
9 months ago
A) True
upvoted 0 times
...
Alpha
9 months ago
B) False
upvoted 0 times
...
Rutha
10 months ago
A) True
upvoted 0 times
...
...
Eleni
11 months ago
Why do you think it's False?
upvoted 0 times
...
Celestina
11 months ago
I disagree, I believe the answer is False.
upvoted 0 times
...
Eleni
11 months ago
I think the answer is True.
upvoted 0 times
...

Save Cancel