How should a Development Team deal with non-functional requirements?
A) Ensure every Increment meets them.
B) Make sure the release department understands these requirements, but it is not the Development Team's responsibility.
C) Handle them during the Integration Sprint preceding the Release Sprint.
D) Assign them to the lead developers on the team.

Scrum PSM-I Exam - Topic 2 Question 107 Discussion

Actual exam question for Scrum's PSM-I exam
Question #: 107
Topic #: 2
[All PSM-I Questions]

How should a Development Team deal with non-functional requirements?

Show Suggested Answer Hide Answer
Suggested Answer: A

The correct answer is A, because the Scrum Guide states that ''the definition of 'Done' is a formal description of the state of the Increment when it meets the quality measures required for the product.'' Therefore, non-functional requirements should be part of the definition of 'Done' and ensure every Increment meets them.


Contribute your Thoughts:

0/2000 characters
Gerald
4 days ago
I think we had a similar question about handling non-functional requirements in a sprint. If I recall correctly, it was about addressing them throughout the development process, not just in a specific sprint.
upvoted 0 times
...
Stephen
9 days ago
I'm not entirely sure, but I feel like we practiced a question where it mentioned that the Development Team is responsible for these requirements. Was that in the context of Agile?
upvoted 0 times
...
Bettyann
14 days ago
I remember we discussed that non-functional requirements should be integrated into every Increment, so I think option A makes sense.
upvoted 0 times
...

Save Cancel