Scrum PSM-I Exam - Topic 2 Question 105 Discussion

Posted by Xenia on Jun 29, 2026 at 11:41 AM

A product Increment must be released to production at the end of each Sprint.

Suggested Answer: B

The correct answer is B, because a product Increment does not have to be released to production at the end of each Sprint. The Scrum Guide states that ''at the end of a Sprint, the new Increment must be 'Done,' which means it must be in useable condition and meet the Scrum Team's definition of 'Done'. An increment is a body of inspectable, done work that supports empiricism at the end of the Sprint. The increment is a step toward a vision or goal.'' Therefore, a product Increment must be potentially releasable, but the decision to release it is up to the Product Owner.


Get Premium PSM-I Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
21 comments · newest first
JE
Jenelle 2 days ago
Releasing Edelmirary time can be overwhelming.
ME
Melynda 7 days ago
B) False allows for flexibility in dEdelmiralopment.
ED
Edelmira 12 days ago
I feel A) True is more aligned with Agile principles.
AZ
Azalee 18 days ago
But not every Sprint has a releasable product.
AM
Amira 23 days ago
True makes sense for continuous delivery.
AM
Amie 28 days ago
I disagree, B) False.
AN
Andree 1 month ago
I think it's A) True.
JE
Jeannetta 1 month ago
Really? I’m not sure that’s always practical.
MO
Mozell 1 month ago
That's how we keep the momentum going!
DA
Daniel 2 months ago
I thought it was optional, not mandatory.
FR
Francene 2 months ago
Totally agree, it should be released every Sprint!
LA
Lashunda 2 months ago
A product increment is supposed to be potentially shippable.
NI
Nickie 2 months ago
I thought it was mandatory to release, interesting!
KI
King 2 months ago
False! Not every Sprint needs a release.
LA
Lashon 2 months ago
Wait, isn't it okay to skip a release sometimes?
KR
Kristel 3 months ago
Totally agree, that's the whole point of Agile!
DA
Danica 3 months ago
A product increment should be released every Sprint.
KA
Karol 3 months ago
I’m leaning towards true, but I remember discussing how it’s more about delivering value rather than just releasing something every time.
MI
Mike 3 months ago
I feel like the Scrum Guide mentioned something about potentially releasing increments, but I can't recall if it was mandatory for every Sprint.
EL
Elliott 3 months ago
I remember a practice question about this, and I think the answer was false because not every increment has to go live immediately.
KI
Kimi 4 months ago
I think it's true that a product increment must be released, but I'm not entirely sure if it has to be in every Sprint.
0/2000 characters

Save Cancel