Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?
(choose the best two answers)
Suggested Answer: A, B
Get Premium PSK-I Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
During a flow-based Daily Scrum, the team is likely to review metrics such as Work Item Age and Work in Progress (WIP):
* Work Item Age: Helps to identify items that have been in progress for a longer time than expected, signaling possible impediments or the need for swarming to complete those items.
* Work in Progress (WIP): Indicates the number of items currently being worked on, ensuring that the team is not exceeding the agreed WIP limits, which is crucial for maintaining a steady flow
12 comments · newest first
CA
Cathrine
1 month ago
A and F make sense to me. Work Item Age shows progress.
DE
Deeanna
1 month ago
I prefer D and E. Lead Time is crucial!
CH
Chandra
1 month ago
I think A and B are key metrics.
SO
Sonia
2 months ago
Not sure about Cycle Time being reviewed daily.
BE
Bettye
2 months ago
Agree, WIP is a must-have metric.
EL
Elizabeth
2 months ago
Surprised Work Item Age isn't on the list!
MA
Marcelle
2 months ago
I think Lead Time is more relevant.
CA
Candra
2 months ago
Definitely WIP and Cycle Time!
CA
Candida
2 months ago
I practiced a question similar to this, and I think Velocity is often discussed, but I’m not sure if it’s the best choice here.
KA
Kate
3 months ago
I feel like Cycle Time could be relevant as well, but I can't recall if it's specifically mentioned for Daily Scrums.
BE
Ben
3 months ago
I'm a bit unsure, but I remember something about Lead Time being important too. It might show how quickly we can deliver work.
MI
Ming
3 months ago
I think Work in Progress (WIP) is definitely one of the metrics we should focus on during the Daily Scrum. It helps us understand our current workload.