Who must change the Work in Progress (WIP) Limits in the Definition of Workflow when urgent
work emerges from the Sprint?
(choose the best answer)
In Professional Scrum with Kanban, the Work in Progress (WIP) limits are set as a policy to maintain a sustainable flow of work. Urgent work emerging does not automatically warrant changing these WIP limits; instead, the team should first discuss how to accommodate the urgent work within the existing constraints. Modifying WIP limits for urgent work could undermine the benefits of a controlled flow, which is why urgent work should not be a reason to change WIP limits during a Sprint