Which of the following are lagging indicator metrics?
(choose the best three answers)
Lagging indicator metrics are metrics that provide information about past performance:
1. Velocity (Option A): This is a measure of the amount of work a Scrum Team completes in a Sprint. It is a lagging indicator because it reflects what has been done rather than predicting future performance.
2. Cycle Time (Option B): This metric measures the time taken to complete a work item from start to finish. It is a lagging indicator because it provides data on how long work items took to complete in the past.
3. Throughput (Option D): This refers to the number of work items completed in a given period. Like Velocity, it reflects past performance and is considered a lagging indicator.
Work in Progress (Option C) and Work Item Aging (Option E) are not lagging indicators:
* Work in Progress (C): is a current state metric that indicates how much work is currently in progress.
* Work Item Aging (E): is a leading indicator, providing insights into how long a work item has been in progress, helping predict delays or bottlenecks
Andra
2 months agoMarvel
2 months agoPamella
3 months agoDalene
3 months agoSabra
3 months agoRichelle
3 months agoCarlton
4 months agoNenita
4 months agoMonte
4 months agoLillian
4 months agoLayla
4 months agoTerrilyn
4 months agoMollie
5 months agoTammara
5 months agoHeidy
6 months agoChauncey
7 months ago