Scrum PSK-I Exam - Topic 2 Question 23 Discussion

Posted by Thomasena on May 31, 2026 at 06:58 AM

Scrum Teams using Kanban can start to increase predictability by:

(choose the best answer)

Suggested Answer: D

Scrum Teams using Kanban can start to increase predictability by reducing the amount of work in progress (WIP) through WIP limits. This approach helps to limit the number of items being worked on at any given time, thus reducing multitasking and context switching. It allows the team to focus on completing a few items before starting new ones, which directly impacts the flow of work and helps to predict when items will be completed. By controlling the WIP, teams can achieve a steady flow of work, improve cycle times, and make more reliable forecasts about future deliveries


Get Premium PSK-I Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
17 comments · newest first
EV
Evangelina 23 days ago
All options have merit, but A stands out for predictability.
VI
Vince 28 days ago
I still feel C is important for overall Scrum health.
IS
Isidra 1 month ago
Right, A and B together could be powerful.
OR
Oretha 1 month ago
True, but without visualization, it’s hard to track.
EV
Evangelina 1 month ago
D is crucial too. WIP limits really help manage flow.
VI
Vince 2 months ago
C seems off. Sprint Review is not about Kanban.
IS
Isidra 2 months ago
I agree, but B offers more tools for transparency.
OR
Oretha 2 months ago
I think A is the best choice. Visualizing helps everyone see progress.
DE
Della 2 months ago
C) is more about the review, not really Kanban-related.
DE
Desmond 2 months ago
Wait, can Kanban really boost predictability? Sounds too good to be true.
NI
Nina 2 months ago
D) makes sense, less WIP means more focus.
KE
Kenneth 3 months ago
I think B) is super important too, can't overlook those charts.
CA
Candra 3 months ago
A) is definitely key for visualizing tasks!
ER
Erasmo 3 months ago
I feel like inspecting the Product Backlog during the Sprint Review is more about adapting than predictability, but I could be wrong.
LA
Lanie 3 months ago
Reducing WIP limits sounds familiar from our practice questions, and it seems like it could definitely help with predictability.
JO
Josephine 3 months ago
I remember we discussed how Control Charts can help with predictability, but I can't recall if that's the main focus here.
JO
Jolene 4 months ago
I think visualizing the workflow with a Kanban board is really important, but I'm not sure if it's the best answer for increasing predictability.
0/2000 characters

Save Cancel