Scaled Agile Exam SAFe-SASM Topic 7 Question 27 Discussion

Actual exam question for Scaled Agile's SAFe-SASM exam
Question #: 27
Topic #: 7
[All SAFe-SASM Questions]

A Scrum Master is asked to help an Agile Release Train that has struggled through multiple Pls. They just finished the second Iteration in the current PI and have nothing to show at the System Demo. The ART stakeholders are concerned. What should be done?

Show Suggested Answer Hide Answer
Suggested Answer: A

Problem Statement: The ART has nothing to show at the System Demo, indicating potential issues with integration, quality, or coordination among teams.

Recommended Action: Stopping new development work to focus on integrating and testing the system allows the team to identify and resolve integration issues, ensuring that the system is in a stable state.

Scope Adjustment: Based on what is learned during integration and testing, the scope can be adjusted to focus on delivering a coherent and functional system increment.

SAFe Scrum Master Reference:

SAFe emphasizes the importance of a stable, integrated system increment to demonstrate progress and ensure quality. Addressing integration issues promptly is crucial for maintaining stakeholder confidence and delivering value.


Contribute your Thoughts:

Derick
3 hours ago
Option B? Really? Showing off individual team increments? That's like a chef presenting individual ingredients instead of the whole meal. Nah, not gonna fly.
upvoted 0 times
...
Kasandra
3 days ago
Option A is the way to go. No more new features, just focus on integration and testing. Gotta get that system working, baby!
upvoted 0 times
...