Scaled Agile SAFe-SASM Exam - Topic 5 Question 41 Discussion

Which two events provide opportunities for the team to collaborate? (Choose two.)
A) Iteration Planning and E) Backlog refinement
B) Portfolio Sync
C) Solution Demo
D) Pre-PI Planning

Scaled Agile SAFe-SASM Exam - Topic 5 Question 41 Discussion

Actual exam question for Scaled Agile's SAFe-SASM exam
Question #: 41
Topic #: 5
[All SAFe-SASM Questions]

Which two events provide opportunities for the team to collaborate? (Choose two.)

Show Suggested Answer Hide Answer
Suggested Answer: A, E

Iteration Planning:

Purpose: Iteration Planning is a crucial event where the team collaborates to determine what will be delivered in the upcoming iteration and how the work will be accomplished. The entire team, including the Scrum Master, Product Owner, and Developers, come together to plan the iteration's work.

Process:

The Product Owner presents the prioritized backlog items to the team.

The team discusses each item, clarifies any ambiguities, and breaks down the items into tasks.

The team estimates the effort required for each task and commits to what they believe can be achieved in the iteration.

Outcome: A detailed iteration plan that includes the selected backlog items and a clear understanding of the tasks and responsibilities for each team member.

Backlog Refinement:

Purpose: Backlog Refinement (also known as Grooming) is an ongoing process where the team and the Product Owner collaborate to review and update the backlog. This ensures that the backlog is in good shape for future iteration planning.

Process:

The team reviews the items in the backlog to ensure they are well understood and ready for future iterations.

The Product Owner provides context and clarifications for each backlog item.

The team discusses the requirements, refines the acceptance criteria, and estimates the effort required for each item.

The backlog items are prioritized based on their value and urgency.

Outcome: A well-maintained and prioritized backlog that facilitates effective and efficient iteration planning.

SAFe Scrum Master Reference:

Iteration Planning:

SAFe Advanced Scrum Master training materials emphasize the importance of Iteration Planning as a key event for team collaboration, ensuring everyone is aligned on the iteration goals and tasks.

2020 Scrum Guide: The Iteration Planning section outlines the collaborative nature of this event and its role in setting the stage for successful iterations.

Backlog Refinement:

In the SAFe framework, Backlog Refinement is highlighted as an essential activity to maintain a healthy backlog, allowing the team to prepare for future iterations effectively.

Scrum Open: This document discusses the significance of Backlog Refinement in fostering team collaboration and ensuring the backlog is well-groomed and ready for planning.


Contribute your Thoughts:

0/2000 characters
Rene
3 days ago
I think A and C are the best choices.
upvoted 0 times
...
Ollie
8 days ago
I’m surprised people aren’t mentioning B more!
upvoted 0 times
...
Svetlana
13 days ago
A and E seem right to me!
upvoted 0 times
...
Shawnta
19 days ago
Wait, are we sure about D? Seems less collaborative.
upvoted 0 times
...
Kati
24 days ago
I think B could also be a good choice.
upvoted 0 times
...
Noemi
29 days ago
Definitely A and C! Those are key for collaboration.
upvoted 0 times
...
Doyle
1 month ago
I’m torn between Backlog refinement and Solution Demo for the second option. Both seem like they involve team input, but I can’t recall which is more collaborative.
upvoted 0 times
...
Gerald
1 month ago
I feel like Pre-PI Planning could be a collaboration opportunity, but I’m not entirely confident. I might lean towards Iteration Planning and Portfolio Sync.
upvoted 0 times
...
Whitley
1 month ago
I remember practicing a question like this, and I think Solution Demo is a good choice too. It’s a chance for feedback, right?
upvoted 0 times
...
Katie
2 months ago
I think Iteration Planning is definitely one of the events where the team collaborates, but I'm not sure about the second one. Maybe Backlog refinement?
upvoted 0 times
...