Scaled Agile SAFe-SASM Exam - Topic 2 Question 37 Discussion

Three teams in the Agile Release Train are working on the same Feature. Team A is a complicated subsystem team, and Teams B and C are stream-aligned teams. During PI Planning, Teams B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with Team A's piece in the first week of the IP Iteration. Why is this an anti-pattern?
D) Because work should not be planned for the IP Iteration
A) Because Product Management accepted each team's final plan at the end of PI Planning Day 2
B) Because each feature team needs to integrate with the component team
C) Because the teams managed their dependencies and planned their integration timing during PI Planning

Scaled Agile SAFe-SASM Exam - Topic 2 Question 37 Discussion

Actual exam question for Scaled Agile's SAFe-SASM exam
Question #: 37
Topic #: 2
[All SAFe-SASM Questions]

Three teams in the Agile Release Train are working on the same Feature. Team A is a complicated subsystem team, and Teams B and C are stream-aligned teams. During PI Planning, Teams B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with Team A's piece in the first week of the IP Iteration. Why is this an anti-pattern?

Show Suggested Answer Hide Answer
Suggested Answer: D

In SAFe, the Innovation and Planning (IP) Iteration is reserved for activities such as innovation, planning, and preparation for the next Program Increment (PI), as well as for holding the Inspect and Adapt (I&A) event. It is not intended for completing work that should have been finished during regular iterations. Planning work for the IP Iteration can lead to a lack of focus on essential planning and innovation activities and may indicate poor planning and risk management practices. Therefore, relying on the IP Iteration to complete Feature work is considered an anti-pattern.

SAFe Scrum Master Reference

SAFe 5.0 framework: guidelines on the purpose and use of the IP Iteration

SAFe Advanced Scrum Master learning materials


Contribute your Thoughts:

0/2000 characters
Timothy
23 days ago
I remember discussing how integration should happen earlier, but I'm not sure if it's really an anti-pattern just because of the timing.
upvoted 0 times
...

Save Cancel