SAP C_TS422_2021 Exam - Topic 7 Question 41 Discussion

Actual exam question for SAP's C_TS422_2021 exam
Question #: 41
Topic #: 7
[All C_TS422_2021 Questions]

You want to insert an operatio at a certain time on work center. The planning direction is forward. The disired dispatching time concides with an operation that has previously been dispatched. How does the insertion take place?

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

0/2000 characters
Rozella
3 months ago
Definitely not D, that would mess everything up!
upvoted 0 times
...
Rosalyn
3 months ago
I’m leaning towards C, but not sure if it’s right.
upvoted 0 times
...
Ardella
3 months ago
Wait, what if the timing overlaps? That seems off.
upvoted 0 times
...
Mabel
4 months ago
Totally agree, A makes the most sense!
upvoted 0 times
...
Lorita
4 months ago
I think it's option A. The new one goes after.
upvoted 0 times
...
Leota
4 months ago
I thought that when inserting operations, the existing ones usually don't get moved backward. So, I'm leaning towards option A or B, but I can't recall the exact details.
upvoted 0 times
...
Quentin
4 months ago
This is tricky! I feel like if the new operation is inserted at the desired time, it might push the previous one forward. Could that be option C?
upvoted 0 times
...
Bettye
4 months ago
I remember practicing a similar question, and I think the previously dispatched operation stays as is. So, maybe it's option A?
upvoted 0 times
...
Tiffiny
5 months ago
I'm a bit unsure about this one. I think the new operation should go after the dispatched one, but I'm not completely confident.
upvoted 0 times
...
Demetra
5 months ago
I'm pretty confident that the correct answer is C. The new operation should be inserted at the desired time, and the previously dispatched operation should be moved forward to accommodate it.
upvoted 0 times
...
Callie
5 months ago
Hmm, I'm a bit confused by the wording here. I'll need to re-read the question and the answer choices a few times to make sure I understand what's being asked.
upvoted 0 times
...
Cordie
5 months ago
This seems like a tricky question. I'll need to think carefully about the implications of the planning direction and the timing of the new operation.
upvoted 0 times
...
Renea
5 months ago
Okay, I think I've got it. The key is the planning direction being forward, so the new operation should be inserted after the previously dispatched one.
upvoted 0 times
...
Shantay
5 months ago
Ah yes, that makes sense. I'm going to go with option A, "Lead token for a Custom Field value," as the incorrect use in this case.
upvoted 0 times
...
Lashawn
9 months ago
I wonder if the exam author has a crystal ball to see into the future and know exactly when these operations will be dispatched. Seems like a lot of guesswork to me!
upvoted 0 times
...
Francine
9 months ago
Option C all the way! Move that previously dispatched operation forward like a boss. Who needs to follow the rules when you can just make your own?
upvoted 0 times
Trevor
8 months ago
D) The new operation is inserted at the desired time; the previously dispatched operation is moved backward.
upvoted 0 times
...
Veronika
8 months ago
C) The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
upvoted 0 times
...
Mirta
8 months ago
B) The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.
upvoted 0 times
...
Dortha
9 months ago
A) The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.
upvoted 0 times
...
...
Jamal
10 months ago
Hmm, this is a tricky one. I'm leaning towards option D, where the new operation is inserted at the desired time and the previously dispatched operation is moved backward. It just seems more straightforward to me.
upvoted 0 times
Desmond
8 months ago
I also believe option A is the right choice. It maintains the order of operations on the work center.
upvoted 0 times
...
Flo
8 months ago
I agree with option A. It makes sense to keep the previously dispatched operation as is.
upvoted 0 times
...
Shelba
9 months ago
I think option A is correct. The new operation is inserted after the previously dispatched operation.
upvoted 0 times
...
...
Cathrine
10 months ago
I'm not sure about this one. Wouldn't it be better to insert the new operation before the previously dispatched one? That way, we don't have to move the existing operation.
upvoted 0 times
Angelyn
8 months ago
I think option B makes more sense. It would be less disruptive to the existing operations.
upvoted 0 times
...
Dante
8 months ago
B) The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.
upvoted 0 times
...
Loreta
8 months ago
A) The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.
upvoted 0 times
...
...
Merissa
10 months ago
Option C seems like the logical choice here. The new operation should be inserted at the desired time, and the previously dispatched operation should be moved forward to accommodate it.
upvoted 0 times
...
Pearly
11 months ago
But if the new operation is inserted at the desired time, wouldn't the previously dispatched operation need to be moved forward to make space?
upvoted 0 times
...
Heike
11 months ago
I disagree, I believe the answer is A.
upvoted 0 times
...
Pearly
11 months ago
I think the answer is C.
upvoted 0 times
...