SAP C_TS422_2021 Exam - Topic 7 Question 25 Discussion

Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing?
A) Posting of production costs to the production cost collector and D) Posting of goods receipt for the product and E) Reduction of associated capacity requirements
B) Material staging for nex order in sequence
C) Archiving of documents for assembly scrap

SAP C_TS422_2021 Exam - Topic 7 Question 25 Discussion

Actual exam question for SAP's C_TS422_2021 exam
Question #: 25
Topic #: 7
[All C_TS422_2021 Questions]

Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing?

Show Suggested Answer Hide Answer
Suggested Answer: A, D, E

Contribute your Thoughts:

0/2000 characters
Van
6 months ago
It's A and D for sure, no doubt about it.
upvoted 0 times
...
Sharmaine
6 months ago
Not sure about B, seems a bit off.
upvoted 0 times
...
Shoshana
7 months ago
Wait, does it really do E by default? That's new to me!
upvoted 0 times
...
Christa
7 months ago
I think it's D, but A sounds right too.
upvoted 0 times
...
Haydee
7 months ago
Definitely A, that's how it works!
upvoted 0 times
...
Myong
7 months ago
I feel like the reduction of capacity requirements is something that happens, but I can't recall if it’s automatic when saving confirmations.
upvoted 0 times
...
Armanda
7 months ago
I’m a bit confused about the material staging part. I thought that was more related to the beginning of the process, not saving confirmations.
upvoted 0 times
...
Kina
8 months ago
I remember practicing a question about goods receipts in repetitive manufacturing, so I feel like option D might be correct.
upvoted 0 times
...
Hubert
8 months ago
I think the system definitely posts production costs to the cost collector when saving confirmations, but I'm not entirely sure if that's the only action.
upvoted 0 times
...
Starr
8 months ago
I'm a bit confused by the wording of the question. I'll need to re-read it a few times to make sure I understand.
upvoted 0 times
...
Stefanie
8 months ago
Posting of production costs, material staging, and goods receipt - those seem like the key actions to focus on.
upvoted 0 times
...
Aracelis
8 months ago
Okay, let me think this through step-by-step. I want to make sure I get the right answer.
upvoted 0 times
...
Kristal
8 months ago
Hmm, I'm not too sure about this one. I'll have to read through the options carefully.
upvoted 0 times
...
Art
8 months ago
This question seems straightforward, I think I can handle it.
upvoted 0 times
...
Ula
8 months ago
Okay, I've got this. GET, PUT, and DELETE are definitely valid HTTP methods. I'm not as confident about Upload, but I'll include it just in case.
upvoted 0 times
...
Lezlie
8 months ago
This question seems straightforward, I think I can handle it.
upvoted 0 times
...
Ilene
8 months ago
I think this question is asking about the specific syntax for the endpoint URL used in the softcoding record setup for a one-view reporting scenario. I'll need to carefully review the options to determine the correct format.
upvoted 0 times
...

Save Cancel