You want to create a quality notification for the Complaint Against Supplier notification origin. Which of the following documents are available as standard in SAP S/4HANA to use as reference documents? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, C

For a 'Complaint Against Supplier' notification (e.g., type Q2, transaction QM01):

Material Document (B): Material documents (e.g., goods receipt via MIGO) are standard references, linking the complaint to a specific receipt event (SPRO > QM > Quality Notifications > Notification Creation).

Purchasing Document (C): Purchase orders (e.g., from ME21N) are commonly referenced to tie the complaint to the supplier's delivery or order.

WBS Element (A): Work Breakdown Structure elements are PS-related, not standard for supplier complaints.

QM Order (D): QM orders track costs but aren't reference documents for notification creation.

Thus, 'Material document' and 'Purchasing document' are the correct answers.


Contribute your Thoughts:

Carlee
29 days ago
Definitely C and D. Gotta love those purchasing and quality orders. They're the bread and butter of any supplier issue.
upvoted 0 times
...
Winfred
1 months ago
Haha, WBS element? Might as well ask about the kitchen sink while you're at it!
upvoted 0 times
Lisha
20 days ago
A) WBS element
upvoted 0 times
...
...
Karima
1 months ago
Material document? What does that have to do with a supplier complaint? This test is tricky!
upvoted 0 times
Ashley
27 days ago
C) Purchasing document
upvoted 0 times
...
Fairy
28 days ago
A) WBS element
upvoted 0 times
...
...
Luann
2 months ago
C and D are the correct answers. Can't go wrong with purchasing and quality docs for a supplier complaint.
upvoted 0 times
Malcolm
30 days ago
Purchasing and quality docs are essential for a supplier complaint.
upvoted 0 times
...
Malcolm
1 months ago
C and D are the correct answers.
upvoted 0 times
...
...
Theola
2 months ago
I'm not sure about Material document. I think WBS element and QM order could also be used as reference documents.
upvoted 0 times
...
Elsa
2 months ago
I agree with Kayleigh. Material document and Purchasing document make sense for reference in this case.
upvoted 0 times
...
Kayleigh
2 months ago
I think the correct answers are B) Material document and C) Purchasing document.