Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question
''You can assign more than one activity element to a network activity.'' According to SAP Help Portal, ''Capacity requirements of a network activity are reduced when the activity is confirmed.'' According to SAP Press4, ''You can assign the same work center to more than one activity on the same network.'' Reference:4
Limited Time Offer
25%
Off
Iola
3 months agoHenriette
3 months agoMarjory
3 months agoWayne
3 months agoShawnee
4 months agoLaura
2 months agoCarin
3 months agoBrigette
3 months agoMargurite
3 months agoBrigette
4 months agoTresa
4 months agoElenora
3 months agoEmogene
3 months agoAlisha
3 months agoFrancine
4 months agoBulah
4 months agoAdrianna
2 months agoAlethea
3 months agoTomas
3 months agoElza
3 months agoAlton
4 months ago