Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 7 Question 49 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 49
Topic #: 7
[All C_TS412_2021 Questions]

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Brigette
2 days ago
I'm not sure about C and E, but A, B, and D seem right to me.
upvoted 0 times
...
Tresa
5 days ago
Option B is incorrect. Activities with the 'Must start on' constraint don't necessarily have negative float time. It depends on the project schedule.
upvoted 0 times
...
Francine
8 days ago
I agree with Alton. A, B, and D make sense to me.
upvoted 0 times
...
Bulah
10 days ago
I think options A, C, and D are correct. Float time can be negative, the float time of WBS elements is calculated by extrapolation, and critical activities have a float time less than or equal to zero.
upvoted 0 times
...
Alton
14 days ago
I think A, B, and D are correct.
upvoted 0 times
...

Save Cancel