SAP C_TS412_2021 Exam - Topic 7 Question 49 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 49
Topic #: 7
[All C_TS412_2021 Questions]

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

Show Suggested Answer Hide Answer

Contribute your Thoughts:

0/2000 characters
Kara
6 days ago
I’m not sure about the negative float part. I thought float time is always non-negative unless there’s a constraint.
upvoted 0 times
...
Lavelle
12 days ago
I remember float time can be tricky, but I think critical activities usually have zero or negative float, right?
upvoted 0 times
...
Serina
17 days ago
This looks tricky, but I'll give it my best shot. I'll start by identifying the true statements and then double-check my work before submitting.
upvoted 0 times
...
Lynelle
23 days ago
I'm a bit confused about the difference between free float and total float. I'll need to review those definitions before selecting the answers.
upvoted 0 times
...
Starr
28 days ago
I've got this! The key is to remember that activities with 'Must start on' constraints always have negative float time. And critical activities by definition have zero or negative float time. I'm confident I can get this right.
upvoted 0 times
...
Rodney
1 month ago
Okay, let me think this through. I know float time can be negative, so that's one correct answer. I'm a bit unsure about the other two, though.
upvoted 0 times
...
Sherita
1 month ago
Hmm, this question seems straightforward, but I want to make sure I understand the concepts of float time and critical activities before selecting the answers.
upvoted 0 times
...
Iola
7 months ago
This question is a real floater, isn't it? I better not sink my chances by getting this wrong!
upvoted 0 times
Henriette
6 months ago
D) By default, critical activities have a float time, which is less than or equal to zero
upvoted 0 times
...
Marjory
6 months ago
B) Activities with the time constraint 'Must start on' always have a negative float time
upvoted 0 times
...
Wayne
6 months ago
A) Float time can be negative
upvoted 0 times
...
...
Shawnee
7 months ago
I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
upvoted 0 times
Laura
5 months ago
User1: I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
upvoted 0 times
...
Carin
6 months ago
User3: By default, critical activities have a float time, which is less than or equal to zero
upvoted 0 times
...
Brigette
6 months ago
User2: Activities with the time constraint 'Must start on' always have a negative float time
upvoted 0 times
...
Margurite
6 months ago
User1: Float time can be negative
upvoted 0 times
...
...
Brigette
7 months ago
I'm not sure about C and E, but A, B, and D seem right to me.
upvoted 0 times
...
Tresa
7 months ago
Option B is incorrect. Activities with the 'Must start on' constraint don't necessarily have negative float time. It depends on the project schedule.
upvoted 0 times
Elenora
6 months ago
E) The maximum size of a free float is as large as the total float of an activity
upvoted 0 times
...
Emogene
6 months ago
C) The float time of WBS elements is calculated by extrapolation
upvoted 0 times
...
Alisha
6 months ago
A) Float time can be negative
upvoted 0 times
...
...
Francine
7 months ago
I agree with Alton. A, B, and D make sense to me.
upvoted 0 times
...
Bulah
7 months ago
I think options A, C, and D are correct. Float time can be negative, the float time of WBS elements is calculated by extrapolation, and critical activities have a float time less than or equal to zero.
upvoted 0 times
Adrianna
5 months ago
So, options A, C, and D are the correct statements about float time.
upvoted 0 times
...
Alethea
6 months ago
I think critical activities having a float time less than or equal to zero makes sense.
upvoted 0 times
...
Tomas
6 months ago
Yes, that's correct. The float time of WBS elements is indeed calculated by extrapolation.
upvoted 0 times
...
Elza
6 months ago
I agree with you, float time can definitely be negative.
upvoted 0 times
...
...
Alton
7 months ago
I think A, B, and D are correct.
upvoted 0 times
...