SAP C_TS412_2021 Exam - Topic 7 Question 49 Discussion

Posted by Felicitas on Mar 06, 2025 at 06:18 AM

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

Get Premium C_TS412_2021 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
34 comments · newest first
CL
Clarinda 11 months ago
Totally agree, free float can be as large as total float!
RE
Reena 11 months ago
Float time can definitely be negative.
DA
Dahlia 11 months ago
I disagree, float time shouldn't be negative!
ST
Stephania 11 months ago
Wait, can float time really be calculated by extrapolation?
ME
Mel 12 months ago
I vaguely recall that activities with 'Must start on' constraints might lead to negative float, but I need to double-check that.
AL
Alisha 12 months ago
I practiced a question similar to this, and I think the maximum size of free float being equal to total float sounds correct.
KA
Kara 1 year ago
I’m not sure about the negative float part. I thought float time is always non-negative unless there’s a constraint.
LA
Lavelle 1 year ago
I remember float time can be tricky, but I think critical activities usually have zero or negative float, right?
SE
Serina 1 year ago
This looks tricky, but I'll give it my best shot. I'll start by identifying the true statements and then double-check my work before submitting.
LY
Lynelle 1 year ago
I'm a bit confused about the difference between free float and total float. I'll need to review those definitions before selecting the answers.
ST
Starr 1 year ago
I've got this! The key is to remember that activities with 'Must start on' constraints always have negative float time. And critical activities by definition have zero or negative float time. I'm confident I can get this right.
RO
Rodney 1 year ago
Okay, let me think this through. I know float time can be negative, so that's one correct answer. I'm a bit unsure about the other two, though.
SH
Sherita 1 year ago
Hmm, this question seems straightforward, but I want to make sure I understand the concepts of float time and critical activities before selecting the answers.
IO
Iola 2 years ago
This question is a real floater, isn't it? I better not sink my chances by getting this wrong!
HE
Henriette 1 year ago
↳ replying to Iola
D) By default, critical activities have a float time, which is less than or equal to zero
MA
Marjory 2 years ago
↳ replying to Iola
B) Activities with the time constraint 'Must start on' always have a negative float time
WA
Wayne 2 years ago
↳ replying to Iola
A) Float time can be negative
SH
Shawnee 2 years ago
I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
LA
Laura 1 year ago
↳ replying to Shawnee
User1: I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
CA
Carin 1 year ago
↳ replying to Shawnee
User3: By default, critical activities have a float time, which is less than or equal to zero
BR
Brigette 2 years ago
↳ replying to Shawnee
User2: Activities with the time constraint 'Must start on' always have a negative float time
MA
Margurite 2 years ago
↳ replying to Shawnee
User1: Float time can be negative
BR
Brigette 2 years ago
I'm not sure about C and E, but A, B, and D seem right to me.
TR
Tresa 2 years ago
Option B is incorrect. Activities with the 'Must start on' constraint don't necessarily have negative float time. It depends on the project schedule.
EL
Elenora 1 year ago
↳ replying to Tresa
E) The maximum size of a free float is as large as the total float of an activity
EM
Emogene 1 year ago
↳ replying to Tresa
C) The float time of WBS elements is calculated by extrapolation
AL
Alisha 2 years ago
↳ replying to Tresa
A) Float time can be negative
FR
Francine 2 years ago
I agree with Alton. A, B, and D make sense to me.
BU
Bulah 2 years ago
I think options A, C, and D are correct. Float time can be negative, the float time of WBS elements is calculated by extrapolation, and critical activities have a float time less than or equal to zero.
AD
Adrianna 1 year ago
↳ replying to Bulah
So, options A, C, and D are the correct statements about float time.
AL
Alethea 1 year ago
↳ replying to Bulah
I think critical activities having a float time less than or equal to zero makes sense.
TO
Tomas 1 year ago
↳ replying to Bulah
Yes, that's correct. The float time of WBS elements is indeed calculated by extrapolation.
EL
Elza 2 years ago
↳ replying to Bulah
I agree with you, float time can definitely be negative.
AL
Alton 2 years ago
I think A, B, and D are correct.