SAP C_TS412_2021 Exam - Topic 7 Question 49 Discussion

Float time is calculated during scheduling.Which of the following statements about float time are correct?Note: There are 3 correct answers to this question
B) Activities with the time constraint 'Must start on' always have a negative float time and C) The float time of WBS elements is calculated by extrapolation and E) The maximum size of a free float is as large as the total float of an activity
A) Float time can be negative
D) By default, critical activities have a float time, which is less than or equal to zero

SAP C_TS412_2021 Exam - Topic 7 Question 49 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 49
Topic #: 7
[All C_TS412_2021 Questions]

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

Show Suggested Answer Hide Answer

Contribute your Thoughts:

0/2000 characters
Clarinda
7 months ago
Totally agree, free float can be as large as total float!
upvoted 0 times
...
Reena
7 months ago
Float time can definitely be negative.
upvoted 0 times
...
Dahlia
8 months ago
I disagree, float time shouldn't be negative!
upvoted 0 times
...
Stephania
8 months ago
Wait, can float time really be calculated by extrapolation?
upvoted 0 times
...
Mel
8 months ago
I vaguely recall that activities with 'Must start on' constraints might lead to negative float, but I need to double-check that.
upvoted 0 times
...
Alisha
8 months ago
I practiced a question similar to this, and I think the maximum size of free float being equal to total float sounds correct.
upvoted 0 times
...
Kara
8 months ago
I’m not sure about the negative float part. I thought float time is always non-negative unless there’s a constraint.
upvoted 0 times
...
Lavelle
9 months ago
I remember float time can be tricky, but I think critical activities usually have zero or negative float, right?
upvoted 0 times
...
Serina
9 months ago
This looks tricky, but I'll give it my best shot. I'll start by identifying the true statements and then double-check my work before submitting.
upvoted 0 times
...
Lynelle
9 months ago
I'm a bit confused about the difference between free float and total float. I'll need to review those definitions before selecting the answers.
upvoted 0 times
...
Starr
9 months ago
I've got this! The key is to remember that activities with 'Must start on' constraints always have negative float time. And critical activities by definition have zero or negative float time. I'm confident I can get this right.
upvoted 0 times
...
Rodney
9 months ago
Okay, let me think this through. I know float time can be negative, so that's one correct answer. I'm a bit unsure about the other two, though.
upvoted 0 times
...
Sherita
10 months ago
Hmm, this question seems straightforward, but I want to make sure I understand the concepts of float time and critical activities before selecting the answers.
upvoted 0 times
...
Iola
1 year ago
This question is a real floater, isn't it? I better not sink my chances by getting this wrong!
upvoted 0 times
Henriette
1 year ago
D) By default, critical activities have a float time, which is less than or equal to zero
upvoted 0 times
...
Marjory
1 year ago
B) Activities with the time constraint 'Must start on' always have a negative float time
upvoted 0 times
...
Wayne
1 year ago
A) Float time can be negative
upvoted 0 times
...
...
Shawnee
1 year ago
I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
upvoted 0 times
Laura
1 year ago
User1: I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
upvoted 0 times
...
Carin
1 year ago
User3: By default, critical activities have a float time, which is less than or equal to zero
upvoted 0 times
...
Brigette
1 year ago
User2: Activities with the time constraint 'Must start on' always have a negative float time
upvoted 0 times
...
Margurite
1 year ago
User1: Float time can be negative
upvoted 0 times
...
...
Brigette
1 year ago
I'm not sure about C and E, but A, B, and D seem right to me.
upvoted 0 times
...
Tresa
1 year ago
Option B is incorrect. Activities with the 'Must start on' constraint don't necessarily have negative float time. It depends on the project schedule.
upvoted 0 times
Elenora
1 year ago
E) The maximum size of a free float is as large as the total float of an activity
upvoted 0 times
...
Emogene
1 year ago
C) The float time of WBS elements is calculated by extrapolation
upvoted 0 times
...
Alisha
1 year ago
A) Float time can be negative
upvoted 0 times
...
...
Francine
1 year ago
I agree with Alton. A, B, and D make sense to me.
upvoted 0 times
...
Bulah
1 year ago
I think options A, C, and D are correct. Float time can be negative, the float time of WBS elements is calculated by extrapolation, and critical activities have a float time less than or equal to zero.
upvoted 0 times
Adrianna
1 year ago
So, options A, C, and D are the correct statements about float time.
upvoted 0 times
...
Alethea
1 year ago
I think critical activities having a float time less than or equal to zero makes sense.
upvoted 0 times
...
Tomas
1 year ago
Yes, that's correct. The float time of WBS elements is indeed calculated by extrapolation.
upvoted 0 times
...
Elza
1 year ago
I agree with you, float time can definitely be negative.
upvoted 0 times
...
...
Alton
1 year ago
I think A, B, and D are correct.
upvoted 0 times
...