Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question
''You can assign more than one activity element to a network activity.'' According to SAP Help Portal, ''Capacity requirements of a network activity are reduced when the activity is confirmed.'' According to SAP Press4, ''You can assign the same work center to more than one activity on the same network.'' Reference:4
Limited Time Offer
25%
Off
Iola
2 months agoHenriette
1 months agoMarjory
1 months agoWayne
1 months agoShawnee
2 months agoLaura
7 days agoCarin
1 months agoBrigette
2 months agoMargurite
2 months agoBrigette
2 months agoTresa
2 months agoElenora
1 months agoEmogene
1 months agoAlisha
2 months agoFrancine
2 months agoBulah
2 months agoAdrianna
21 days agoAlethea
27 days agoTomas
1 months agoElza
1 months agoAlton
3 months ago