New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP C_TS412_2021 Exam - Topic 7 Question 49 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 49
Topic #: 7
[All C_TS412_2021 Questions]

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

Show Suggested Answer Hide Answer

Contribute your Thoughts:

0/2000 characters
Clarinda
2 months ago
Totally agree, free float can be as large as total float!
upvoted 0 times
...
Reena
2 months ago
Float time can definitely be negative.
upvoted 0 times
...
Dahlia
3 months ago
I disagree, float time shouldn't be negative!
upvoted 0 times
...
Stephania
3 months ago
Wait, can float time really be calculated by extrapolation?
upvoted 0 times
...
Mel
3 months ago
I vaguely recall that activities with 'Must start on' constraints might lead to negative float, but I need to double-check that.
upvoted 0 times
...
Alisha
3 months ago
I practiced a question similar to this, and I think the maximum size of free float being equal to total float sounds correct.
upvoted 0 times
...
Kara
4 months ago
I’m not sure about the negative float part. I thought float time is always non-negative unless there’s a constraint.
upvoted 0 times
...
Lavelle
4 months ago
I remember float time can be tricky, but I think critical activities usually have zero or negative float, right?
upvoted 0 times
...
Serina
4 months ago
This looks tricky, but I'll give it my best shot. I'll start by identifying the true statements and then double-check my work before submitting.
upvoted 0 times
...
Lynelle
4 months ago
I'm a bit confused about the difference between free float and total float. I'll need to review those definitions before selecting the answers.
upvoted 0 times
...
Starr
4 months ago
I've got this! The key is to remember that activities with 'Must start on' constraints always have negative float time. And critical activities by definition have zero or negative float time. I'm confident I can get this right.
upvoted 0 times
...
Rodney
5 months ago
Okay, let me think this through. I know float time can be negative, so that's one correct answer. I'm a bit unsure about the other two, though.
upvoted 0 times
...
Sherita
5 months ago
Hmm, this question seems straightforward, but I want to make sure I understand the concepts of float time and critical activities before selecting the answers.
upvoted 0 times
...
Iola
10 months ago
This question is a real floater, isn't it? I better not sink my chances by getting this wrong!
upvoted 0 times
Henriette
9 months ago
D) By default, critical activities have a float time, which is less than or equal to zero
upvoted 0 times
...
Marjory
10 months ago
B) Activities with the time constraint 'Must start on' always have a negative float time
upvoted 0 times
...
Wayne
10 months ago
A) Float time can be negative
upvoted 0 times
...
...
Shawnee
10 months ago
I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
upvoted 0 times
Laura
8 months ago
User1: I agree with the three correct answers, but I'm a bit confused about option E. Isn't the maximum free float the same as the total float?
upvoted 0 times
...
Carin
10 months ago
User3: By default, critical activities have a float time, which is less than or equal to zero
upvoted 0 times
...
Brigette
10 months ago
User2: Activities with the time constraint 'Must start on' always have a negative float time
upvoted 0 times
...
Margurite
10 months ago
User1: Float time can be negative
upvoted 0 times
...
...
Brigette
10 months ago
I'm not sure about C and E, but A, B, and D seem right to me.
upvoted 0 times
...
Tresa
11 months ago
Option B is incorrect. Activities with the 'Must start on' constraint don't necessarily have negative float time. It depends on the project schedule.
upvoted 0 times
Elenora
9 months ago
E) The maximum size of a free float is as large as the total float of an activity
upvoted 0 times
...
Emogene
9 months ago
C) The float time of WBS elements is calculated by extrapolation
upvoted 0 times
...
Alisha
10 months ago
A) Float time can be negative
upvoted 0 times
...
...
Francine
11 months ago
I agree with Alton. A, B, and D make sense to me.
upvoted 0 times
...
Bulah
11 months ago
I think options A, C, and D are correct. Float time can be negative, the float time of WBS elements is calculated by extrapolation, and critical activities have a float time less than or equal to zero.
upvoted 0 times
Adrianna
9 months ago
So, options A, C, and D are the correct statements about float time.
upvoted 0 times
...
Alethea
9 months ago
I think critical activities having a float time less than or equal to zero makes sense.
upvoted 0 times
...
Tomas
9 months ago
Yes, that's correct. The float time of WBS elements is indeed calculated by extrapolation.
upvoted 0 times
...
Elza
10 months ago
I agree with you, float time can definitely be negative.
upvoted 0 times
...
...
Alton
11 months ago
I think A, B, and D are correct.
upvoted 0 times
...

Save Cancel