Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 6 Question 50 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 50
Topic #: 6
[All C_TS412_2021 Questions]

You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: A, D

The possible reasons to check if reductions did not reduce the scheduled duration of all internally-processed activities in your project after overall network scheduling are if the maximum reduction level is less than 100 or if the appropriate reduction type is set in the parameters for network scheduling. Reductions are functions that allow you to reduce the scheduled duration of activities and networks by changing their work or capacity requirements based on various strategies and criteria. Reductions can help you optimize your project schedule and meet deadlines or milestones. The possible reasons to check if reductions did not reduce the scheduled duration of all internally-processed activities in your project after overall network scheduling are:

If the maximum reduction level is less than 100: The maximum reduction level is a parameter that defines how much an activity or a network can be reduced as a percentage of its original duration. The maximum reduction level can be specified in Customizing for Project System under Structures Operative Structures Networks Define Reduction Strategies


Contribute your Thoughts:

Azzie
7 days ago
I think checking if the maximum reduction level is less than 100 is also crucial to determine why the duration did not change.
upvoted 0 times
...
Orville
9 days ago
I believe we should also check if the appropriate reduction type is set in the parameters for network scheduling.
upvoted 0 times
...
Andra
9 days ago
Haha, this is a classic case of 'Garbage in, Garbage out'! You gotta make sure the settings are right in both the header and the individual activities. B and C are the way to go.
upvoted 0 times
...
Pedro
11 days ago
I'm going with B and D. If the reduction strategy is not set correctly in the network header and the parameters, it won't make a difference. This is like trying to run a marathon with your shoes on the wrong feet!
upvoted 0 times
...
Margart
15 days ago
I agree with Francesco. It's important to make sure the reduction strategy is set correctly.
upvoted 0 times
...
Shalon
19 days ago
D is definitely one of the correct answers. The reduction type has to be set correctly in the network scheduling parameters for it to work. This is a tricky one!
upvoted 0 times
Apolonia
2 days ago
I think D is correct. The reduction type needs to be set in the parameters for network scheduling.
upvoted 0 times
...
...
Francesco
24 days ago
I think we should check if the reduction strategy is set in each activity.
upvoted 0 times
...
Soledad
26 days ago
I think the answer is B and C. The reduction strategy needs to be set in the network header and in each activity for it to take effect. Anything less than 100% reduction won't change the overall duration.
upvoted 0 times
...

Save Cancel