Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 6 Question 50 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 50
Topic #: 6
[All C_TS412_2021 Questions]

You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: A, D

The possible reasons to check if reductions did not reduce the scheduled duration of all internally-processed activities in your project after overall network scheduling are if the maximum reduction level is less than 100 or if the appropriate reduction type is set in the parameters for network scheduling. Reductions are functions that allow you to reduce the scheduled duration of activities and networks by changing their work or capacity requirements based on various strategies and criteria. Reductions can help you optimize your project schedule and meet deadlines or milestones. The possible reasons to check if reductions did not reduce the scheduled duration of all internally-processed activities in your project after overall network scheduling are:

If the maximum reduction level is less than 100: The maximum reduction level is a parameter that defines how much an activity or a network can be reduced as a percentage of its original duration. The maximum reduction level can be specified in Customizing for Project System under Structures Operative Structures Networks Define Reduction Strategies


Contribute your Thoughts:

Azzie
2 months ago
I think checking if the maximum reduction level is less than 100 is also crucial to determine why the duration did not change.
upvoted 0 times
...
Orville
2 months ago
I believe we should also check if the appropriate reduction type is set in the parameters for network scheduling.
upvoted 0 times
...
Andra
2 months ago
Haha, this is a classic case of 'Garbage in, Garbage out'! You gotta make sure the settings are right in both the header and the individual activities. B and C are the way to go.
upvoted 0 times
Hui
2 days ago
Yep, making sure the reduction strategy is set correctly is key to seeing the desired changes in duration.
upvoted 0 times
...
Erinn
3 days ago
Always important to double check those settings to avoid any issues with the duration not changing.
upvoted 0 times
...
Salome
4 days ago
Definitely, B and C are the correct answers to ensure the reduction settings are correct.
upvoted 0 times
...
Jody
8 days ago
I agree, you have to check both the header and individual activities for the reduction strategy.
upvoted 0 times
...
Jestine
10 days ago
Yep, making sure the reduction strategy is properly set will help ensure the changes are reflected in the overall network scheduling.
upvoted 0 times
...
Dorethea
11 days ago
Always double-check those settings to avoid any discrepancies in the scheduled duration.
upvoted 0 times
...
Staci
18 days ago
Definitely, B) If the reduction strategy is set in the network header and C) If the reduction strategy is set in each activity are crucial.
upvoted 0 times
...
Wilson
1 months ago
I agree, it's important to check both the header and individual activities for the reduction strategy.
upvoted 0 times
...
...
Pedro
2 months ago
I'm going with B and D. If the reduction strategy is not set correctly in the network header and the parameters, it won't make a difference. This is like trying to run a marathon with your shoes on the wrong feet!
upvoted 0 times
...
Margart
2 months ago
I agree with Francesco. It's important to make sure the reduction strategy is set correctly.
upvoted 0 times
...
Shalon
2 months ago
D is definitely one of the correct answers. The reduction type has to be set correctly in the network scheduling parameters for it to work. This is a tricky one!
upvoted 0 times
Kimi
1 months ago
Good point! So the correct answers are D and C.
upvoted 0 times
...
Nada
1 months ago
Yes, that's right. But don't forget to also check if the reduction strategy is set in each activity.
upvoted 0 times
...
Apolonia
2 months ago
I think D is correct. The reduction type needs to be set in the parameters for network scheduling.
upvoted 0 times
...
...
Francesco
2 months ago
I think we should check if the reduction strategy is set in each activity.
upvoted 0 times
...
Soledad
2 months ago
I think the answer is B and C. The reduction strategy needs to be set in the network header and in each activity for it to take effect. Anything less than 100% reduction won't change the overall duration.
upvoted 0 times
Josue
1 months ago
That's right. Anything less than 100% reduction won't change the overall duration.
upvoted 0 times
...
Vanna
1 months ago
Yes, you're correct. The reduction strategy needs to be set in both the network header and each activity.
upvoted 0 times
...
Francine
2 months ago
I think the answer is B and C.
upvoted 0 times
...
...

Save Cancel