SAP C_TS412_2021 Exam - Topic 5 Question 69 Discussion

Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
A) Goods receipt into unvaluated project stock and C) Goods receipt of a non-stock item
B) Recording of external services in the service entry sheet
D) Goods receipt into valuated project stock

SAP C_TS412_2021 Exam - Topic 5 Question 69 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 69
Topic #: 5
[All C_TS412_2021 Questions]

Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: A, C

Goods receipt into unvaluated project stock and goods receipt of a non-stock item do not lead to the booking of actual costs to an object. Goods receipt into unvaluated project stock does not affect inventory valuation or accounting documents, therefore no actual costs are posted. Goods receipt of a non-stock item does not affect inventory valuation either, but only updates the purchase order history and statistical delivery costs, therefore no actual costs are posted. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html