You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question
Availability control is a function that monitors whether the budget for a project is sufficient for planned and actual costs. Availability control can be activated in different ways depending on the settings in the availability control profile and the tolerance limits. Some of these ways are:
Automatic activation with budget assignment: Availability control is activated when you assign budget to a WBS element or a network activity.
Automatic activation with the first actual posting: Availability control is activated when you post the first actual cost to a WBS element or a network activity. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334
Holley
10 months agoReiko
10 months agoBarrett
10 months agoGerri
11 months agoRaelene
11 months agoChristene
11 months agoBeckie
11 months agoElenora
11 months agoLynsey
11 months agoRyan
12 months agoCandida
12 months agoTasia
12 months agoColby
12 months agoLaurel
12 months agoMicah
12 months agoLettie
2 years agoEva
2 years agoMalissa
2 years agoAlyce
2 years agoJules
2 years agoLazaro
2 years agoPeggie
2 years agoVon
2 years agoDenny
2 years ago