Which planning method can prevent further rescheduling of activities?

Suggested Answer: A

Partial confirmation of activities is a planning method that allows you to confirm a part of an activity's duration or work. This prevents further rescheduling of the activity because the confirmed part is fixed and cannot be changed. The remaining part of the activity can still be rescheduled according to the project progress and resource availability. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html


Get Premium C_TS412_2021 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
0 comments · newest first

Currently there are no comments in this discussion, be the first to comment!

0/2000 characters

Save Cancel