You want to create a reservation for a material component assigned to a network activity.

However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing

reservation?

Note: There are 2 correct answers to this question

Show Suggested Answer Hide Answer

Contribute your Thoughts:

0/2000 characters
Ezekiel
3 months ago
I disagree with D, non-stock can still have reservations sometimes.
upvoted 0 times
...
Karan
3 months ago
D makes sense too, non-stock materials don’t get reservations.
upvoted 0 times
...
Tequila
3 months ago
Wait, can C really be true? 'Never' seems extreme!
upvoted 0 times
...
Alaine
4 months ago
I think B is also correct, external procurement messes things up.
upvoted 0 times
...
Gianna
4 months ago
A is definitely a reason, missing parts can block reservations.
upvoted 0 times
...
Nan
4 months ago
I’m a bit lost on this one, but I wonder if D could be correct since non-stock materials might not create reservations like stock materials do.
upvoted 0 times
...
Dong
4 months ago
I practiced a similar question, and I think if the Reservation/Purchase Requisition indicator is set to 'never', that could definitely stop a reservation. So C seems likely.
upvoted 0 times
...
Precious
4 months ago
I’m not entirely sure, but I think if the material master is set to external procurement, it could prevent a reservation from being created. So maybe B is right?
upvoted 0 times
...
Luis
5 months ago
I remember something about the availability check possibly affecting reservations, so A might be a correct answer.
upvoted 0 times
...
Mattie
5 months ago
Non-stock material, huh? I hadn't considered that. I'll make sure to check that as well.
upvoted 0 times
...
Tu
5 months ago
Okay, let me think this through step-by-step. I'll go through each of the possible reasons and see which one fits best.
upvoted 0 times
...
Phillip
5 months ago
Ah, I bet it's the reservation indicator. That's a common gotcha that can trip you up if you're not aware of it.
upvoted 0 times
...
Coleen
5 months ago
The availability check and procurement method seem like the most likely culprits here. I'll double-check those first.
upvoted 0 times
...
Tandra
5 months ago
Hmm, this is a tricky one. I'll need to carefully review the material master and activity settings to identify the issue.
upvoted 0 times
...
Craig
10 months ago
I wonder if the material gods are playing a practical joke on us. Where's the 'summon the material guru' button when you need it?
upvoted 0 times
...
Sonia
10 months ago
I bet the material master is set to external procurement. That would be a real knee-slapper if that's the issue. Time to do some digging!
upvoted 0 times
Brock
8 months ago
User 3: Let's check that setting to see if that's the issue.
upvoted 0 times
...
Alisha
9 months ago
User 2: Yeah, that could be the reason why the reservation is missing.
upvoted 0 times
...
Coral
9 months ago
User 1: I think the material master is set to external procurement.
upvoted 0 times
...
...
Rashida
10 months ago
The 'never' reservation indicator? Sounds like someone forgot to flip the switch on that one. Classic material management problem right there.
upvoted 0 times
Gwen
9 months ago
Yeah, the 'never' reservation indicator could definitely be the reason. Someone should check that setting.
upvoted 0 times
...
Julianna
9 months ago
It could also be because the material master is set to external procurement.
upvoted 0 times
...
Dominque
9 months ago
I think the missing reservation could be due to the availability check indicating missing parts.
upvoted 0 times
...
...
Lauran
10 months ago
Wait, the material is a non-stock item? That would definitely explain the missing reservation. I should have paid closer attention to that detail.
upvoted 0 times
Alaine
9 months ago
It's important to pay attention to all the details when creating reservations for material components.
upvoted 0 times
...
Myong
10 months ago
Make sure to check the Reservation/Purchase Requisition indicator for the material component as well.
upvoted 0 times
...
Mitsue
10 months ago
Yes, if the material is assigned as a non-stock item, no reservation will be created.
upvoted 0 times
...
...
Skye
11 months ago
Hmm, looks like I need to check the availability and procurement settings for the material component. This is tricky, but I'm sure I can figure it out.
upvoted 0 times
Lettie
10 months ago
B) The material master is set to external procurement
upvoted 0 times
...
Elfriede
10 months ago
A) The availability check for material components indicates missing parts
upvoted 0 times
...
...
Adria
11 months ago
I think the availability check for material components indicating missing parts could also be a reason for the missing reservation.
upvoted 0 times
...
Alexia
11 months ago
I agree with Alonso. Another possible reason could be that the indicator Reservation/Purchase Requisition for the material component is set to 'never'.
upvoted 0 times
...
Alonso
11 months ago
I think the missing reservation could be due to the material master being set to external procurement.
upvoted 0 times
...