SAP Exam C_TS412_2021 Topic 3 Question 23 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 23
Topic #: 3
[All C_TS412_2021 Questions]

Cost & budget

A service Company use project management and they complain that the system does not prevent their project manager from

exceeding their budget.

What action do you have tsolve the problem?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Yolande
4 days ago
Option B looks good, but I'm worried about the administrative overhead of defining tolerance limits for each WBS element. Is that really scalable?
upvoted 0 times
...
Bernadine
8 days ago
I'm not sure if option D is the best choice. Entering the budget in the master data might be too high-level and not provide the granular control needed.
upvoted 0 times
...
Chauncey
22 days ago
Option C seems like the most straightforward approach. Defining the tolerance limits in the customizing settings should provide the necessary controls to prevent budget overruns.
upvoted 0 times
Latosha
9 hours ago
User 2: Yeah, defining the tolerance limits in the customizing settings should help prevent budget overruns.
upvoted 0 times
...
Donte
1 days ago
User 1: I think option C is the best solution.
upvoted 0 times
...
...
Teddy
26 days ago
I believe activating commitment would also be a good solution to the problem.
upvoted 0 times
...
Annice
1 months ago
I agree with Sherill, entering plan data for each WBS element will help prevent exceeding the budget.
upvoted 0 times
...
Sherill
1 months ago
I think we should activate availability control for projects in the control area.
upvoted 0 times
...