SAP C_TS412_2021 Exam - Topic 2 Question 71 Discussion

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
B) Enter February 10 as fixed date
A) Enter an offset of -18 days to the finish date of the activity
C) Enter 10 days as duration
D) Enter an offset of 10 days to the start date of the activity

SAP C_TS412_2021 Exam - Topic 2 Question 71 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 71
Topic #: 2
[All C_TS412_2021 Questions]

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?

Show Suggested Answer Hide Answer
Suggested Answer: B

To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding activities or milestones. A fixed date can be entered manually or automatically derived from a constraint. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html