SAP C_TS412_2021 Exam - Topic 2 Question 48 Discussion
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?Note : there are 2 correct answers for this question.
A) Use an offset of two days for the relationship of both activities. and D) Calculate the start date of the activity and set the constraint 'Must start on' accordingly.
B) Use an offset of two days for milestone date.
C) Use an offset of two days for the requirement date of the material component
Eric
6 months agoDaniel
6 months agoFrancesco
7 months agoMaurine
7 months agoCamellia
7 months agoGerald
7 months agoMargarett
7 months agoKandis
8 months agoKristian
8 months agoEve
8 months agoGregg
8 months agoStevie
8 months agoEzekiel
8 months agoTom
8 months agoRefugia
1 year agoFreeman
1 year agoTora
1 year agoLashon
1 year agoTy
1 year agoFlo
1 year agoMaryann
1 year agoDominic
1 year agoCatalina
1 year agoSylvie
1 year agoAlfred
1 year agoReynalda
1 year agoCassi
1 year agoAlesia
1 year agoTruman
1 year agoEffie
1 year agoAilene
1 year ago