SAP C_TS412_2021 Exam - Topic 2 Question 48 Discussion
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?Note : there are 2 correct answers for this question.
A) Use an offset of two days for the relationship of both activities. and D) Calculate the start date of the activity and set the constraint 'Must start on' accordingly.
B) Use an offset of two days for milestone date.
C) Use an offset of two days for the requirement date of the material component
Eric
10 months agoDaniel
10 months agoFrancesco
10 months agoMaurine
11 months agoCamellia
11 months agoGerald
11 months agoMargarett
11 months agoKandis
11 months agoKristian
11 months agoEve
11 months agoGregg
11 months agoStevie
11 months agoEzekiel
11 months agoTom
12 months agoRefugia
2 years agoFreeman
2 years agoTora
2 years agoLashon
2 years agoTy
2 years agoFlo
2 years agoMaryann
2 years agoDominic
2 years agoCatalina
2 years agoSylvie
2 years agoAlfred
2 years agoReynalda
1 year agoCassi
2 years agoAlesia
2 years agoTruman
2 years agoEffie
2 years agoAilene
2 years ago