Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 2 Question 21 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 21
Topic #: 2
[All C_TS412_2021 Questions]

The various work packages in the project are described as individual______________. Choose the correct answer.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Brittni
28 days ago
Wait, wait, wait... are we talking about the Work Breakdown Structure or the Breakfast Burrito Structure? Because in that case, I'd go with D) Activities - as in, 'activities I plan to do with this delicious breakfast burrito'.
upvoted 0 times
...
Amber
1 months ago
C) Tasks? What is this, a middle school math problem? WBS elements all the way, baby!
upvoted 0 times
...
Linette
1 months ago
D) Activities? Nah, that's too generic. The question is specifically asking about the work packages, so A) WBS elements is the way to go.
upvoted 0 times
Leigha
12 days ago
I think A) WBS elements is the correct answer.
upvoted 0 times
...
...
Salley
2 months ago
I was thinking B) Project definitions, but now that I think about it, that doesn't really make sense in the context of the question. WBS elements sounds more appropriate.
upvoted 0 times
Stevie
12 days ago
Yes, WBS elements are the individual components of the work breakdown structure.
upvoted 0 times
...
Gail
14 days ago
I agree, WBS elements make more sense in this context.
upvoted 0 times
...
Candra
1 months ago
I think A) WBS elements is the correct answer.
upvoted 0 times
...
...
Giovanna
2 months ago
I'm not sure, but I think it could also be D) Activities because work packages can be broken down into smaller activities.
upvoted 0 times
...
Ashley
2 months ago
A) WBS elements definitely sounds like the correct answer. I mean, the work packages are the building blocks of the Work Breakdown Structure, aren't they?
upvoted 0 times
Fernanda
1 months ago
D) Activities are related to work packages, but they are not the same as work packages themselves.
upvoted 0 times
...
Lisandra
1 months ago
C) Tasks are part of work packages, but they are not the same thing.
upvoted 0 times
...
Kris
1 months ago
B) Project definitions are important, but they are not the same as work packages.
upvoted 0 times
...
Merilyn
1 months ago
A) WBS elements are indeed the individual components that make up the Work Breakdown Structure.
upvoted 0 times
...
...
Iraida
2 months ago
I agree with Marti, work packages are usually broken down into WBS elements.
upvoted 0 times
...
Marti
3 months ago
I think the answer is A) WBS elements.
upvoted 0 times
...
Sheron
3 months ago
I'm not sure, but I think it could also be D) Activities because work packages can be broken down into smaller activities.
upvoted 0 times
...
Isabelle
3 months ago
I agree with Rex, work packages are usually broken down into WBS elements.
upvoted 0 times
...
Rex
3 months ago
I think the answer is A) WBS elements.
upvoted 0 times
...

Save Cancel