Wait, wait, wait... are we talking about the Work Breakdown Structure or the Breakfast Burrito Structure? Because in that case, I'd go with D) Activities - as in, 'activities I plan to do with this delicious breakfast burrito'.
I was thinking B) Project definitions, but now that I think about it, that doesn't really make sense in the context of the question. WBS elements sounds more appropriate.
A) WBS elements definitely sounds like the correct answer. I mean, the work packages are the building blocks of the Work Breakdown Structure, aren't they?
Brittni
28 days agoAmber
1 months agoLinette
1 months agoLeigha
12 days agoSalley
2 months agoStevie
12 days agoGail
14 days agoCandra
1 months agoGiovanna
2 months agoAshley
2 months agoFernanda
1 months agoLisandra
1 months agoKris
1 months agoMerilyn
1 months agoIraida
2 months agoMarti
3 months agoSheron
3 months agoIsabelle
3 months agoRex
3 months ago