SAP C_TS412_2021 Exam - Topic 1 Question 2 Discussion
Project StructuresYou are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to theproject.What are the prerequisites?Note: There are 3 correct answers to this question
B) A material master with sales views and C) Assignment between material and standard network and D) Standard network with activities
A) A bill of material with sales views
E) A production order