Project StructureYou plan double the work on each internal activity for multiple project. What do you recommend?
A) Use mass change (CNMASS) in the project system.
B) Double the work of each internal activity, one after another, in the project Builder.
C) Double the capacity in the work center.
D) Use mass change within the project Builder (CJ20N).

SAP C_TS412_2021 Exam - Topic 1 Question 1 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 1
Topic #: 1
[All C_TS412_2021 Questions]

Project Structure

You plan double the work on each internal activity for multiple project. What do you recommend?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Lizbeth
7 months ago
Isn't doubling the work a bit much? What if it backfires?
upvoted 0 times
...
Kenneth
7 months ago
A is a solid option too, but I prefer D for flexibility.
upvoted 0 times
...
Rodolfo
7 months ago
Wait, can you really double everything at once? Sounds risky.
upvoted 0 times
...
Mari
7 months ago
Definitely agree with D, it's more efficient!
upvoted 0 times
...
Barb
8 months ago
I think option D is the best choice for mass changes.
upvoted 0 times
...
Janey
8 months ago
I recall we discussed the importance of work center capacity, but doubling it like in option C seems a bit off for this scenario.
upvoted 0 times
...
Ardella
8 months ago
I feel like doubling the work in the project Builder one by one, as in option B, could be really tedious. Is that the best approach?
upvoted 0 times
...
Theodora
8 months ago
I'm not entirely sure, but I remember something about using CNMASS for bulk changes. Could that be option A?
upvoted 0 times
...
Lindy
8 months ago
I think option D might be the right choice since it mentions mass change in the project Builder, which we practiced in class.
upvoted 0 times
...
Christene
8 months ago
Hmm, I'm not sure about this one. I know the Segment Join to Journey Builder feature is used to connect a journey to a segment, but I can't remember the specific entry source event type that needs to be configured. I'll have to think this through carefully.
upvoted 0 times
...
Rikki
8 months ago
This is a tricky one. There are a lot of networking and security components involved in VMware Cloud Director. I'll need to really think through the logical flow of enabling the east/west firewall and match that to the options provided.
upvoted 0 times
...
Enola
8 months ago
Hmm, this looks like a tricky one. I'll need to carefully read through the question and options to figure out the right configuration for R2.
upvoted 0 times
...
Art
8 months ago
I remember practicing a question that mentioned "Engineer-to-order" having longer lead times, which makes me lean towards "Make-to-stock," but I'm still second-guessing.
upvoted 0 times
...
Refugia
8 months ago
Okay, let me see here. I think the key is understanding how the Time Until UP and Manual Resume settings work in this scenario. I'll need to review those carefully.
upvoted 0 times
...
Elise
8 months ago
Hmm, I'm a bit unsure about the differences between Multi-Pod and Multi-Site setups. Let me think this through carefully.
upvoted 0 times
...

Save Cancel