Which controlling objects can be settled by a settlement rule in SAP S/4HANA? Note: There are 3 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: B

Posting External Labor Costs: In SAP, external labor costs, such as those from subcontractors or external services, can be posted to network activities (part of Project Systems or Plant Maintenance) to capture the costs associated with external services.

Service Entry Sheet as a Mechanism:

Service Documentation: The service entry sheet is used to record the details of services provided by external vendors, including labor hours, rates, and total cost.

Cost Posting: Upon approval, the service entry sheet triggers the posting of external labor costs to the relevant network activity, ensuring accurate cost allocation and tracking.

Implementation in SAP: In the Project System (PS) or Plant Maintenance (PM) modules, service entry sheets are created and managed to document and approve external services, which are then associated with specific network activities for cost tracking.


SAP Project System (PS) Configuration Guide

SAP Plant Maintenance (PM) Guide

Contribute your Thoughts:

Joanna
2 days ago
A, B, and D? Piece of cake! Settlement rules are like the traffic cops of the SAP world, making sure everything stays in its lane.
upvoted 0 times
...
Trina
3 days ago
Well, I'm stumped. I was certain that B, D, and E were the right answers, but now I'm not so sure. Maybe I need to revisit my notes on settlement rules in S/4HANA.
upvoted 0 times
...
Ming
7 days ago
I think A, C, and E are the right options. Settlement rules can be used to control production orders, WBS elements, and profit centers, right?
upvoted 0 times
...
Honey
9 days ago
I'm pretty sure A, B, and D are the correct answers. Settlement rules are used to control production orders, maintenance orders, and sales orders, but not WBS elements or profit centers.
upvoted 0 times
...
Van
13 days ago
I'm not sure about sales order and profit center. I think they are not settled using settlement rules.
upvoted 0 times
...
Susana
13 days ago
I agree with Jame. Those objects are usually settled in SAP S/4HANA.
upvoted 0 times
...
Jame
15 days ago
I think production order, maintenance order, and WBS element can be settled.