In a project, what is the correct term for a group of dependencies, activities, and relationships sequenced in chronological order?

Show Suggested Answer Hide Answer
Suggested Answer: D

In the context of project management within SAP, the correct term for a group of dependencies, activities, and relationships sequenced in chronological order is a Network (D). Networks are used to represent the logical and temporal sequence of tasks within a project, enabling detailed planning, execution, and monitoring of project activities.

A Work Breakdown Structure (A) is used to structure the project into manageable sections, but it does not inherently define the chronological sequence of activities.

Project Planning (B) is a broad term that encompasses all aspects of planning within a project, including the creation of networks and work breakdown structures, but it is not a specific object or element within SAP.

Routing (C) is more commonly associated with manufacturing processes in SAP and defines the sequence of operations required to produce a product.


Contribute your Thoughts:

Jacki
25 days ago
Hey, I thought this was an exam, not a choose-your-own-adventure book! I'm picking E) Interpretive dance, because that's how I plan my projects.
upvoted 0 times
Keneth
24 hours ago
B) Project planning
upvoted 0 times
...
Gianna
16 days ago
A) Work breakdown structure
upvoted 0 times
...
...
Karol
1 months ago
Wow, this is a tough one. I'll go with C) Routing, just because it sounds like it could be something to do with project workflows.
upvoted 0 times
Deonna
24 hours ago
I agree with you, C) Routing sounds like it could be related to project workflows.
upvoted 0 times
...
Marylyn
16 days ago
I'll choose B) Project planning.
upvoted 0 times
...
Salley
18 days ago
I'm going with D) Network.
upvoted 0 times
...
Vannessa
30 days ago
I think it's A) Work breakdown structure.
upvoted 0 times
...
...
Donte
1 months ago
I'm not sure, but D) Network also sounds like it could be the correct term for sequencing activities.
upvoted 0 times
...
Craig
2 months ago
I agree with Latosha. Work breakdown structure makes sense for organizing dependencies and activities.
upvoted 0 times
...
Latosha
2 months ago
I think the correct term is A) Work breakdown structure.
upvoted 0 times
...
Leatha
2 months ago
Hmm, I'm leaning towards B) Project planning. Isn't that where you outline the whole project workflow?
upvoted 0 times
Kaitlyn
18 days ago
I think it's D) Network, because it shows the relationships between tasks.
upvoted 0 times
...
Mona
21 days ago
Yes, you're right. Project planning is where we outline the workflow.
upvoted 0 times
...
...
Elvera
2 months ago
Gotta be A) Work breakdown structure. That's the go-to for breaking down project tasks, right?
upvoted 0 times
C) Routing is not the right answer. The correct term is A) Work breakdown structure.
upvoted 0 times
...
Kattie
2 days ago
D) Network is not the correct term for this. It's A) Work breakdown structure.
upvoted 0 times
...
Aleisha
8 days ago
B) Project planning is important too, but the term we're looking for is A) Work breakdown structure.
upvoted 0 times
...
Lawana
28 days ago
A) Work breakdown structure is correct. It helps organize project tasks.
upvoted 0 times
...
...
Shawana
2 months ago
I'm pretty sure it's D) Network. That's the classic term for sequencing dependencies and activities in a project.
upvoted 0 times
...

Save Cancel