Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS410_2022 Topic 13 Question 35 Discussion

Actual exam question for SAP's C_TS410_2022 exam
Question #: 35
Topic #: 13
[All C_TS410_2022 Questions]

In a project, what is the correct term for a group of dependencies, activities, and relationships sequenced in chronological order?

Show Suggested Answer Hide Answer
Suggested Answer: D

In the context of project management within SAP, the correct term for a group of dependencies, activities, and relationships sequenced in chronological order is a Network (D). Networks are used to represent the logical and temporal sequence of tasks within a project, enabling detailed planning, execution, and monitoring of project activities.

A Work Breakdown Structure (A) is used to structure the project into manageable sections, but it does not inherently define the chronological sequence of activities.

Project Planning (B) is a broad term that encompasses all aspects of planning within a project, including the creation of networks and work breakdown structures, but it is not a specific object or element within SAP.

Routing (C) is more commonly associated with manufacturing processes in SAP and defines the sequence of operations required to produce a product.


Contribute your Thoughts:

Jacki
1 months ago
Hey, I thought this was an exam, not a choose-your-own-adventure book! I'm picking E) Interpretive dance, because that's how I plan my projects.
upvoted 0 times
Apolonia
16 days ago
D) Network
upvoted 0 times
...
Deeann
17 days ago
C) Routing
upvoted 0 times
...
Keneth
19 days ago
B) Project planning
upvoted 0 times
...
Gianna
1 months ago
A) Work breakdown structure
upvoted 0 times
...
...
Karol
2 months ago
Wow, this is a tough one. I'll go with C) Routing, just because it sounds like it could be something to do with project workflows.
upvoted 0 times
Deonna
19 days ago
I agree with you, C) Routing sounds like it could be related to project workflows.
upvoted 0 times
...
Marylyn
1 months ago
I'll choose B) Project planning.
upvoted 0 times
...
Salley
1 months ago
I'm going with D) Network.
upvoted 0 times
...
Vannessa
2 months ago
I think it's A) Work breakdown structure.
upvoted 0 times
...
...
Donte
2 months ago
I'm not sure, but D) Network also sounds like it could be the correct term for sequencing activities.
upvoted 0 times
...
Craig
2 months ago
I agree with Latosha. Work breakdown structure makes sense for organizing dependencies and activities.
upvoted 0 times
...
Latosha
2 months ago
I think the correct term is A) Work breakdown structure.
upvoted 0 times
...
Leatha
2 months ago
Hmm, I'm leaning towards B) Project planning. Isn't that where you outline the whole project workflow?
upvoted 0 times
Kaitlyn
1 months ago
I think it's D) Network, because it shows the relationships between tasks.
upvoted 0 times
...
Mona
1 months ago
Yes, you're right. Project planning is where we outline the workflow.
upvoted 0 times
...
...
Elvera
2 months ago
Gotta be A) Work breakdown structure. That's the go-to for breaking down project tasks, right?
upvoted 0 times
Dick
14 days ago
The work breakdown structure helps in understanding the project scope better.
upvoted 0 times
...
Melissa
15 days ago
It's essential to have a clear breakdown of work to stay on track.
upvoted 0 times
...
Sharan
16 days ago
I always use the work breakdown structure to organize my project tasks.
upvoted 0 times
...
Truman
17 days ago
Yes, you're right! A) Work breakdown structure is the correct term for that.
upvoted 0 times
...
Gail
18 days ago
C) Routing is not the right answer. The correct term is A) Work breakdown structure.
upvoted 0 times
...
Kattie
20 days ago
D) Network is not the correct term for this. It's A) Work breakdown structure.
upvoted 0 times
...
Aleisha
26 days ago
B) Project planning is important too, but the term we're looking for is A) Work breakdown structure.
upvoted 0 times
...
Lawana
2 months ago
A) Work breakdown structure is correct. It helps organize project tasks.
upvoted 0 times
...
...
Shawana
2 months ago
I'm pretty sure it's D) Network. That's the classic term for sequencing dependencies and activities in a project.
upvoted 0 times
...

Save Cancel