Which of the following object help to support automatic creation between portfolio and project management (PPM) and project system (PS)?

NOTE: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

Jacquelyne
28 days ago
I bet the correct answers are 'PS Sudoku' and 'PS Flappy Bird'. Gotta keep those project managers entertained, you know?
upvoted 0 times
...
Jamey
29 days ago
This question is making me feel like I'm back in school. Time to put on my thinking cap and get this right!
upvoted 0 times
Donette
13 days ago
B) PS network
upvoted 0 times
...
Glendora
17 days ago
A) PS profile
upvoted 0 times
...
...
Royal
1 months ago
C has to be wrong - a 'PS standard project'? What, are they trying to standardize my coffee order now?
upvoted 0 times
...
Cyndy
1 months ago
I was thrown off by the 'PS network' option. Sounds like some kind of social media for project managers!
upvoted 0 times
...
Kristel
1 months ago
A and D seem like the obvious choices here. The PS profile and PS operative project are key for integrating PPM and PS.
upvoted 0 times
Elza
8 days ago
D) PS operative project
upvoted 0 times
...
Caprice
13 days ago
A) PS profile
upvoted 0 times
...
...
Hayley
2 months ago
I'm not sure about the correct answers. Can someone explain why PS profile and PS network are the right choices?
upvoted 0 times
...
Irma
2 months ago
I agree with Carman. PS profile and PS network are the objects that support automatic creation between PPM and PS.
upvoted 0 times
...
Carman
2 months ago
I think the correct answers are A) PS profile and B) PS network.